NSEAnalysts/Institutional Investor Meet/Con. Call Updates4d ago · 27 Aug 2026, 05:34 pm
Analysts/Institutional Investor Meet/Con. Call Updates
Globe Civil Projects Limited · GLOBECIVIL
✦ AI Summary▲ PositiveResults
Globe Civil Projects Limited held an earnings conference call to discuss its Q1 FY 27 performance, reporting a 37.26% year-on-year growth in total income to INR929.23 million and a 33.03% growth in EBITDA to INR15.80 crores.
Analysis Scores
Earnings Impact8/10
Growth Catalyst6/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment8/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Globe Civil Projects Limited has informed the Exchange about Transcript
Attachments (1)
📄pdf
Download →
GLOBE2024_27082026173409_Intimation_Transcript.pdf
View document text
Email : info@globecivilprojects.in
< =< '-‘ Web : www.globecivilprojects.com
Tel : 011- 4656 1560
Globe Civil Projects Limited
August 27,2026
To To
National Stock Exchange of India Ltd BSE Limited
Listing Compliance Department Listing Compliance Department
Exchange Plaza, 5th Floor, C. 1, Block G, | st Floor, Phiroze Jeejeebhoy Towers, Dalal
Bandra Kurla Complex, Bandra (E), Mumbai | Street Mumbai — 400001
400051
NSE SYMBOL: GLOBECIVIL SCRIP CODE: 544424
SUBJECT: TRANSCRIPT OF INVESTORS MEET HELD ON AUGUST 25, 2026 AT 4:00
P.M.
Dear Sir/Madam,
Pursuant to Regulation 30 and 46 of the Securities and Exchange Board of India (Listing
Obligations and Disclosure Requirements) Regulations, 2015, please find enclosed Transcript of
the Investors meet held on August 25, 2026 at 04:00 P.M.
The above details are also being made available on the Company's website at
www.globecivilprojects.com
This is for your information and record please.
Thanking you,
For GLOBE CIVIL PROJECTS LIMITED
Vineet Digelysignea
byVineet Rattan
Date:2026.08.27
Rattan issesosso
VINEET RATTAN
Company Secretary and Compliance Officer
Membership Number: F 11724
L45202DL2002PLC115486
khla Industrial Area,
aQacr
Globe Civil Projects Lid.
“Globe Civil Projects Limited
QI and FY '27 Earnings Conference Call”
August 25, 2026
(< (e} @
EquiBridgeX cnen v
/ Advisors Pvt Ltd
Globe Civil Projects Ltd
MANAGEMENT: MR. VIPUL KHURANA — MANAGING DIRECTOR —
GLOBE CIVIL PROJECTS LIMITED
MR. RAGHAV AGGARWAL — CHIEF FINANCIAL
OFFICER — GLOBE CIVIL PROJECTS LIMITED
MODERATOR: MR. GAUTAM NAGAR — EQUIBRIDGEX ADVISORS
PRIVATE LIMITED
Page 1 0f13
Globe Civil Projects Limited
Globe Civil Projects Ltd August 25, 2026
Ladies and gentlemen, good day, and welcome to Globe Civil Projects Limited Q1 and FY 27
Moderator:
Earnings Conference Call hosted by EquiBridgeX Advisors Private Limited. As a reminder, all
participants will be in the listen-only mode and there will be an opportunity for you to ask
questions after the presentation concludes. Should you need assistance during the conference
call, please signal an operator by pressing star then zero on your touch transform.
Please note that this conference is being recorded. I now hand the conference over to Mr. Gautam
Nagar from EquiBridgeX. Thank you, and over to you, Gautam.
Gautam Nagar: Thank you. A very good evening to everyone. Welcome to the Q1 FY 27 Earnings Call of Globe
Civil Projects Limited. From the management team, we have with us Mr. Vipul Khurana,
Managing Director, and Mr. Raghav Aggarwal, Chief Financial Officer. We will have opening
remarks from the management team, post which we'll open the floor for the Q&A. With that, T
would like to hand over the call to management for the opening remarks. Over to you, sir.
Vipul Khurana: Good evening, everyone. This is Vipul Khurana, Managing Director of Globe Civil Projects
Limited. Thank you for joining us today for the eamings call to discuss the company's
performance for the first quarter of FY "27. We truly appreciate the time and interest of our
investors, analysts and all other stakeholders.
Globe Civil Projects Limited is an EPC-focused infrastructure company engaged in the
exccution of civil and infrastructure projects across India. Our work covers a range of projects,
including infrastructure, facilities, buildings and allied civil works. Over the years, we have built
our business around disciplined project execution, efficient resource utilization and timely
delivery, supported by our experienced managemetneatm and established execution capabilities.
During the first quarter of FY '27, the company delivered a steady performance supported by
continued progress across our ongoing EPC projects and efficient utilization of resources. We
remain focused on execution and project delivery while continuing work across our diverse
project portfolio.
Our presence continues to be spread across different segments of infrastructure, including
education, health care, housing, sports, commercial and transportation infrastructure. We also
continue to work with institutional and government-linked clients, including CPWD, NBCC,
IITs and other institutions. This diversified project portfolio gives us the opportunity to
participate across different categories of civil and infrastructure development.
During the quarter, our focus remains on disciplined execution, efficient project management
and timely progress across the ongoing projects. As an EPC business, execution remains at the
center of our operation, and we continue to focus on maintaining quality, cost efficiency and
delivery time line across our project.
With this brief overview of our business, I would now like to hand over the call to Mr. Raghav
Aggarwal, our Chief Financial Officer, who will take you through the financial performance of
the quarter in greater details. Thank you, and over to Raghav.
Page 2 0f 13
Globe Civil Projects Limited
Globe Civil Projects Ltd August 25, 2026
Raghav Aggarwal: Thank you, Vipul sir. 'm Raghav Aggarwal, CFO of the company. Good evening, everyone. Let
me now take you through the financial performance of the company for the quarter ended June
30,2026. On a consolidated basis, the company reported a total income of INR929.23 million
during quarter 1 financial year '27 compared with INR676.98 million in quarter 1 financial year
2026, representing a growth of 37.26% year-on-year.
EBITDA for the quarter stood at INR15.80 crores compared to INR11.88 crores corresponding
quarter of the previous financial year, registering a growth of 33.03%. The EBITDA margin for
the quarter stood at 17.01%. Profit after tax stood at INR7.09 crores compared to INR5.05 crores
in quarter 1 of last year, representing a growth of 40.42% year-on-year.
The net profit margin stood at 7.63%. Overall, the quarter reflects steady progress across the
company’s ongoing projects and continued focus on operational efficiency and disciplined
exccution. We remain focused on efficient project management, timely execution and prudent
‘management of our business operations across the project portfolio. The infrastructure sector in
India continues to benefit from government-led capital expenditure, increased focus on roads,
urban infrastructure and public works, providing a supportive demand environment for EPC
companies.
Within this environment, Globe Civil Projects Limited remains focused on strengthening
exccution capability, improving working capital efficiency and selectively pursuing
opportunities aligned with its risk framework. Thank you for joining us today for your interest
in Globe Civil Projects Limited. We will now open the floor for the questions.
Thank you so much, sir, for your opening remarks. Ladies and gentlemen, we will now begin
Moderator:
with the question-and-answer session. The first question comes from the line of Riya Sharma,
an Individual Investor. Please go ahead.
Riya Sharma: Congratulations for your Q1 results. T have a few questions. So my first question is revenue grew
strongly in Q1 FY2027. What were the main factors behind this performance?
Raghav Aggarwal: The main factor was the projects we got after the IPO listing, we got three projects, Central
University at Bathinda, Haryana Cricket Association and Kanpur. So we have received — we
have achieved an order book of INR1,000 crores in the month of August 2025. So that was the
key that we have projects - after the IPO, we were able to bid projects, EPC bigger projects and
that materialized after -- because any project which we get, it takes at least six to seven months
to start and give revenue in full flow.
Vipul Khurana: In fact, the cricket stadium took time to start. That's why it was less than we were expecting even
better revenue, better performance. But yes, sometimes the projects to get started to get some
approvals are pending, which takes time initially.
Raghav Aggarwal: Otherwise, we would have achieved a better turnover in last year also, but cricket stadium started