R.P.P. Infra Projects Limited · RPPINFRA
✦ AI SummaryOrder Cancel
R.P.P. Infra Projects Limited has informed the Exchange regarding the termination of a work order from Sports Development Authority of Tamil Nadu for the Establishment of Global Sports City, Chennai, worth Rs. 205,89,14,000, due to the decision to restructure and redesign the project.
Analysis Scores
Earnings Impact5/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk3/10
Balance Sheet Risk6/10
Liquidity Impact5/10
Market Sentiment4/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
R.P.P. Infra Projects Limited has informed the Exchange regarding 'Termination of Work Order from Sports Development Authority of Tamil Nadu'.
Attachments (1)
📄pdf
Download →
RPPINFRA_27082026170207_SDAT_Termination-SE_Intimation.pdf
View document text
»))))
= RPP Infra Projects Limited
Date: 27th August 2026
Department of Corporate Services, Compliance Department,
BSE Limited (BSE) National Stock Exchange of India Limited (NSE)
25t Floor, Phiroze JeeJeeBhoy Towers, Exchange Plaza, Plot No. C-1, Block G,
Dalal Street, Fort, Bandra Kurla Complex, Bandra (East)
Mumbai - 400001 Mumbai - 400051
Scrip Code: 533284 NSE Symbol: RPPINFRA
ISIN: INE324L01013 ISIN: INE324L01013
Dear Sir/Madam
Subject: Termination of work order - intimation pursuant to Regulation 30 of the
SEBI (Listing Obligations and Disclosure Requirements) Regulations 2015
This is to inform you that the Company had earlier, vide its letter dated 20t February
2026, intimated the Stock Exchanges regarding the receipt of a work order from Sports
Development Authority of Tamil Nadu (SDAT) for Establishment of Global Sports City,
Chennai. The value of the work order is Rs. 205,89,14,000/- (Rupees Two Hundred and
Five Crores Eighty-Nine Lakhs and Fourteen Thousand only), including GST @ 18%.
The Company has received a communication from SDAT regarding termination of the
aforesaid work order, pursuant to the decision to restructure and redesign the Global
Sports City project considering the total extent of land available, in order to develop a
bigger, comprehensive and all-encompassing Sports City capable of hosting future
National and International level sporting events, including events of the scale of the Asian
Games.
The communication regarding termination of the work order was received by the
Company on 12t August 2026. The Company had commenced activities pursuant to the
aforesaid work order and has incurred substantial expenditure towards the project.
Subsequent to the change in the State Government, the concerned authorities undertook
areview of various projects and work orders, pursuant to which the aforesaid work order
was terminated by SDAT.
The Company had been engaging with SDAT regarding the continuation ofthe projectand
had made efforts to pursue the same. However, the work order was subsequently
terminated by SDAT.
Regd Office: Corporate Office: CIN: L45201T1995PLC006113
SF.No. 454, Raghupafiynaiken Palayam, 0Ozone Premia, 6 Floor,
Railway Colony (Po), Poondurai Road, New No. 39, Dr. Radha Krishnan Salai,
Erode — 638002. Tamilnadu. India. Mylapore, Chennai — 600 004. Tamilnadu. India.
: 20@rppipl.com | : www.rppipl.com B : cco@rppipl.com | : www.rppipl.com
[ : 04242284077 [ 10446929 2771/72/73/74/75
»))))
= RPP Infra Projects Limited
The Company is evaluating the financial and other implications arising from the
termination, including its rights and remedies under the terms of the work
order/contract.
In view of the aforesaid circumstances, including the Company's efforts towards
continuation of the project and the expenditure already incurred, there was an
inadvertent delay in making the requisite disclosure to the Stock Exchanges. The
Company has accordingly made the present disclosure and regrets the delay.
Disclosure is being made pursuant to Regulation 30 of SEBI (LODR) Regulations, 2015
read with SEBI Master Circular No. SEBI/HO/CFD/PoD2/CIR/P/0155 dated November
11,2024 as Annexure A
We request you to take the same on record
Thanking You,
Yours Faithfully,
For R.P.P Infra Projects Limited
ISelvam
Company Secretary & Compliance Officer
Regd Office: Corporate Office: CIN: L45201T1995PLC006113
SF.No. 454, Raghupafiynaiken Palayam, 0Ozone Premia, 6 Floor,
Railway Colony (Po), Poondurai Road, New No. 39, Dr. Radha Krishnan Salai,
Erode — 638002. Tamilnadu. India. Mylapore, Chennai — 600 004. Tamilnadu. India.
: 20@rppipl.com | : www.rppipl.com B : cco@rppipl.com | : www.rppipl.com
[ : 04242284077 [ 10446929 2771/72/73/74/75
RPP Infra Projects Limited
Annexure A
Disclosure pursuant to Regulation 30 of SEBI (LODR) Regulations, 2015 read with SEBI
Master Circular No. SEBI/HO/CFD/PoD2/CIR/P/0155 dated November 11, 2024
Sl No | Particulars Details of the Projects
1 Name of parties to the Sports Development Authority of Tamil Nadu
order(s)/contract(s)
2 Nature of the Establishment of Global Sports City, Chennai -
order(s)/contract(s) appointment of Contractor for design,
Engineering, procurement and construction of
Global Sports City
3 Date of execution of the 18 months from the date of handing over of
order(s)/contract(s) the site
4 Details of amendment or Under the Chairmanship of the Hon’ble
reasons for terminations Minister for Public Works and Sports
and impact thereof (to the Development, it was decided to restructure
extent possible); and redesign the Global Sports City project
considering the total extent of land available,
in order to develop a bigger, comprehensive
and all-encompassing Sports City capable of
hosting future National and International level
Sporting events, including events of the scale
of the Asian Games. Hence, the termination is
issued to the Company. The Company had
commenced activities pursuant to the
aforesaid work order and has incurred
substantial expenditure towards the project.
The Company is evaluating the financial and
other implications arising from the
termination, including its rights and remedies
under the terms of the work order/contract.
Regd Office: Corporate Office: CIN: 145201T1995PLCO06113
SF.No. 454, Raghupafiynaiken Palayam, 0Ozone Premia, 6 Floor,
Railway Colony (Po), Poondurai Road, New No. 39, Dr. Radha Krishnan Salai,
Erode — 638002. Tamilnadu. India. Mylapore, Chennai — 600 004. Tamilnadu. India.
: 20@rppipl.com | : www.rppipl.com B : cco@rppipl.com | £ : www.rppipl.com
[ 104242284077 [ : 0446929 2771/72/73/74/75
SOIPETE aflenemm-® GUDLUTLE SOLen6eUTWLILD
SPORTS DEVELOPMENT AUTHORITY OF TAMIL NADU
Jawaharlal Nehru Stadium, Raja Muthiah Road,Periyamet, Chennai - 600003, Tamil Nadu
Phone : +91 44 2561 1522Isdat@tn.gov.mwaw.sdat.tn gov.in
J. Meghanatha Reddy, I.A.S., «
Member Secretary Y
Rc.No. 4899/TD-1/2021, Dated:31.07.2026 @
M/s.RPP Infra Projects Limited,
SF 454, Ragupathinaiyaken Palayam,
Poondurai Road, Erode-638 002.
project@rppipl.com
Sir,
Sub: SDAT- Establishment of Global Sports City, Chennai -
Appointment of Contractor for Design, Engineering,
Procurement & Construction of Global Sports City (EPC Mode-
I) - Work Order issued to M/s. RPP Infra Projects Limited —
Termination of Work Order - Orders - Issued.
Ref: 1. G.0.Ms.No.124, YWR&SD (S2) Dept. Dated: 27.10.2025.
2. This office work order No. 4899/TD-1/2021,
Dated 18:02:2026
3. Minutes of the Meeting on the Proposed Development of
the Global Sports City at Chennai, held on 16.06.2026
under the Chairmanship of the Hon'ble Minister for
Public Works and Sports Development
Work order was issued to M/s.RPP Infra Projects Limited, Poondurai Road,
Erode for the work of “Establishment of Global Sports City, Chennai - Appointment
of Contractor for Design, Engineering, Procurement & Construction of Global
Sports City (EPC 1 Mode)” for the negotiated value of Rs.205,89,14,000/- (Rupees
two hundred and five crore eighty-nine lakh and fourteen thousand only) including
GST @ 18% vide ref.2" cited.
2) Subsequently, in the meeting held on 16.06.2026 under the
Chairmanship of the Hon'ble Minister for Public Works and Sports Development, it
was decided to comprehensively restructure and redesign the Global Sports City
project considering the total extent of land available, in order to develop a bigger,
comprehensive and all-encompassing Sports City capable of hosting future
National and International level sporting events, including events of the scale of
the Asian Games. The outcome of this meeting was briefed to the Contractor M/s
RPP Infra Projects Limited on 18.06.2026.
3) In view of the above policy decision of the Government and the
resolutions recorded in the Minutes of the Meeting dated 16.06.2026, and in
exercise of the powers conferred under clause 55 "No Compensation for
Cancellation / Reduction of Works", Clause 68.4- "Cancellation/Determination of
Contract in Full or Part", Clause 71.0 “Force Majure” and other relevant c