Disclosure Under Regulation 30 of SEBI (LODR) ragarding capacity addition - Purchase of plant and machineries and setting up manufacturing facilities.
Shilp Gravures Ltd-$ · 513709
✦ AI Summary▲ PositiveExpansion
Shilp Gravures Ltd has announced a capacity addition plan, including the purchase of plant and machineries and setting up manufacturing facilities in Karnataka. The investment is expected to be around Rs. 5,71,00,000 plus applicable taxes, and the facility is expected to be commenced during FY 2026-27.
Analysis Scores
Earnings Impact6/10
Growth Catalyst8/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact9/10
Market Sentiment8/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Shilp Gravures Ltd-$ - 513709 - Capacity Addition - Announcement Under Regulation 30 Of SEBI (LODR)
Attachments (1)
📄pdf
Download →
3a25f24f-6b9a-4643-ac7b-ce706ad19bea.pdf
View document text
Date: 17/08/2026
The Manager, DCS-CRD
Corporate Relationship Department,
BSE Limited,
Phiroze Jeejeebhoy Tower,
Dalal Street, Mumbai- 400 001
SECURITY CODE: 513709 || ISIN: INE960A01017
Dear Sir / Madam,
Sub: Disclosure under Regulation 30 of SEBI (Listing Obligations and Disclosure
Requirements) Regulations, 2015 (“SEBI Listing Regulations”).
We wish to inform you that the Board of Directors of the Company, at its meeting held
on today, i.e. August 17, 2026, has approved the following proposed capacity
expansion:
1. Purchase of plant and machineries and to set up manufacturing facilities at
Karnataka.
The details, as required under Regulation 30 of SEBI Listing Regulations read with
SEBI Master Circular No. HO/49/14/14(7)2025-CFD-POD2/I/3762/2026 dated January
30, 2026, are enclosed as Annexure A.
Kindly take the above on record. This disclosure is in compliance with the applicable
provisions of the SEBI Listing Regulations.
Thanking you,
Yours faithfully,
For Shilp Gravures Limited
Jay Chavda
Company Secretary &
Compliance Officer
Membership No.: F14040
Encl: a/a
Annexure A
Sr. Particulars Information
1. Existing capacity Total existing capacity is approximately
94,000 gravure cylinder per year at
Rakanpur, Dist. Gandhinagar, Gujarat as
of 17th August 2026.
2. Existing capacity utilization Capacity utilization of approximately
75,000 gravure cylinder per year.
3. Proposed capacity addition The Board of Directors of the Company at
its meeting held today, i.e. 17th August
2026, has approved investment of around
Rs. 5,71,00,000/- plus applicable taxes
and related charges for the purchase of
plant and machineries at Karnataka and
additional Rs. 1,00,00,000/- for all kind of
expenses and advances related to
commencement of manufacturing facility,
which at full utilisation can produce more
than 18,000 gravure cylinder per year.
4. Period within which the proposed Manufacturing facility is expected to be
capacity is to be added commenced during the FY 2026-27.
5. Investment required The Board of Directors has approved an
investment of around Rs. 5,71,00,000/-
plus applicable taxes and related charges
for the purchase of plant and machineries
at Karnataka and additional Rs.
1,00,00,000/- for all kind of expenses and
advances related to commencement of
manufacturing facility.
6. Mode of financing Internal accruals
7. Rationale This investment is necessary for the
Company's readiness towards long term
growth prospects.