Mangalam Organics Limited has informed the Exchange about Disruption of Operations due to a fire incident at its Camphor Plant I. The appointed Insurance Surveyor has completed the assessment of the loss, and the claim amount submitted to the Insurer is Rs. 12.58 Crore. The Company is actively pursuing the matter with the insurer for the final settlement and disbursement of the Insurance claim.
Analysis Scores
Earnings Impact5/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk3/10
Balance Sheet Risk6/10
Liquidity Impact4/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Mangalam Organics Limited has informed the Exchange about Disruption of Operations due to the fire incident that occurred on July 16, 2025, at its Camphor Plant I located Khopoli, the appointed Insurance Surveyor has completed the assessment of the loss arising out of the aforesaid fire incident and has submitted the final survey report to the Insurer.
Attachments (1)
📄pdf
Download →
MANORG_03072026181738_INTIMATION_ON_UPDATE_OF_FIRE_INCIDENT.pdf
View document text
Registered Office / Factory :
Village Kumbhivali, Savroli-
Kharpada Road, Khalapur-410 202,
Dist. Raigad
(Maharashtra) Tel.
02192 - 276140
Date: July 03, 2026
BSE Limited The National Stock Exchange of India Limited
Listing & Compliance Department Listing & Compliance Department
Phiroze Jeejeebhoy Towers, Exchange Plaza, C-1 Block G,
Dalal Street, Fort Bandra Kurla Complex,
Mumbai – 400001. Bandra (E), Mumbai – 400051
Scrip: 514418 Symbol: MANORG
Dear Sir/Madam,
Subject: Intimation under Regulation 30 read Para B, Part A with Schedule III of the SEBI (Listing
Obligations and Disclosure Requirements) Regulations, 2015
Ref: Intimation of fire incident that occurred on July 16, 2025, at the Company's Camphor Plant I,
located at Kumbhivali Village, Khopoli.
Pursuant to Regulation 30 read with Para B, Part A of Schedule III of the SEBI (Listing Obligations and
Disclosure Requirements) Regulations, 2015 and in continuation of our earlier disclosure dated July 17,
2025, whereby the Company had informed the Stock Exchanges regarding the fire incident that
occurred on July 16, 2025, at its Camphor Plant I located at Kumbhivali Village, Savroli Kharpada Road,
Khopoli – 410203, District Raigad, Maharashtra.
We wish to update you that the appointed Insurance Surveyor has completed the assessment of the
loss arising out of the aforesaid fire incident and has submitted the final survey report to the Insurer,
The New India Assurance Company Limited.
As per the survey report, the loss assessed by the Insurance surveyor and the corresponding Insurance
claim submitted to the insurer amounts to Rs. 12.58 Crore (Rupees Twelve Crore and Fifty-Eight Lakhs
only).
The Company is actively pursuing the matter with the insurer for the final settlement and disbursement
of the Insurance claim. No amount has been realized by the Company as on the date of this disclosure.
Detailed information in accordance with SEBI Circular No. HO/49/14/14(7)2025-CFD-
POD2/I/3762/2026 dated July 11, 2023 and last updated on January 30, 2026, is enclosed herewith as
Annexure-A.
Yours faithfully,
For Mangalam Organics Limited
Charmi Shah
Company Secretary & Compliance Officer
Encl : Annexure-A
An ISO
9001/14001/45001
2018 Certified
Company
Registered Office / Factory :
Village Kumbhivali, Savroli-
Kharpada Road, Khalapur-410 202,
Dist. Raigad
(Maharashtra) Tel.
02192 - 276140
Annexure-A
Disclosure pursuant to Regulation 30 read with the SEBI Master Circular No. HO/49/14/14(7)2025-
CFD-POD2/I/3762/2026 dated July 11, 2023, and last updated on January 30, 2026 in respect of the
fire incident
Particulars Details
expected quantum of loss/damage caused As assessed by the Insurance surveyor, the claim
amount submitted to the Insurer is Rs.12.58
Crore.
whether loss/damage covered by insurance or Yes, the loss is covered under the Company's
not including amount Insurance policy, subject to the terms and
conditions thereof.
The claim amount assessed and submitted is
Rs.12.58 Crore.
estimated impact on the Not applicable
production/operations in case of
strikes/lock outs;
factory/unit where the strike/lock out Not applicable
takes place including reasons for such
strike.
insurance amount claimed and realized by the Insurance claim of Rs.12.58 Crore has been
listed entity for the loss/damage; submitted. No amount has been realized on the
date of this disclosure.
the actual amount of damage caused due to the The Insurance surveyor has completed the
natural calamity or other force assessment of the loss arising from the fire
majeure events incident. The claim assessed and submitted to
the Insurer amounts to Rs. 12.58 Crore.
details of steps taken to restore normalcy and The Company had taken necessary steps to
the impact of the natural calamity/other force restore normal operations. There is no further
majeure events on production or service, material update from the disclosures already
financials of the entity. made in this regard.