✦ AI Summary▼ NegativeDebt Restruc.
Siti Networks Limited has informed the Exchange regarding default on payment of interest/repayment of principal amount on loans from Bank(s) and the reinstatement of Corporate Insolvency Resolution Process (CIRP) of the company.
Analysis Scores
Earnings Impact2/10
Growth Catalyst1/10
Governance Concern6/10
Regulatory Risk8/10
Balance Sheet Risk9/10
Liquidity Impact2/10
Market Sentiment1/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Siti Networks Limited has informed the Exchange regarding 'Disclosure in compliance with Para 3(C2) of SEBI Circular No. SEBI/HO/CFD/CMD1/CIR/2019/140 dated November 21, 2019, of default on payment of interest/repayment of principal amount on loans from Bank(s)'.
Attachments (1)
📄pdf
Download →
SITINET_02072026125706_Default_Intimation_Quarterly_June_30_2026.pdf
View document text
July 2, 2026
The General Manager The Manager
Corporate Relationship Department Listing Department
BSE Limited National Stock Exchange of India limited
Phiroze Jeejeeboy Towers Plaza, 5th Floor, Plot no. C/1, G Block
Dalal Street, Fort, Bandra Kurla Complex, Bandra (E)
Mumbai- 400 001 Mumbai- 400 051
BSE Scrip Code: 532795 NSE Scrip Symbol: SITINET
Kind Attn. : Corporate Relationship Department
Subject : Disclosure in compliance with Para 3(C2) of SEBI Circular No.
SEBI/HO/CFD/CMD1/CIR/2019/140 dated November 21, 2019, of default on
payment of interest/repayment of principal amount on loans from Bank(s)
Dear Sir,
This is in reference to the SEBI Circular No. SEBI/HO/CFD/CMD1/CIR/2019/140 dated November
21, 2019, regarding disclosure of defaults on payment of interest/repayment of principal amount on
loans from Bank(s).
In compliance with Para 3(C2) of above referred SEBI Circulars (i.e. quarterly disclosure), details
pertaining to loan(s) are as follows:
Sl. No. Particulars in INR crore
Amount of Amount of
Claim Claim
submitted as submitted as
on 10th August on 22nd
2023 February
2023
1. Loans / revolving facilities like cash credit from banks
/ financial institutions
A. Total loan amount outstanding as on date (i.e. June 30, 1,206.03 1,500.00
2026)
B. Of the total amount outstanding, amount of default as on
date (i.e. June 30, 2026)
Total Claims received (Including Interest and penal 1,206.03 1,500.00
Interest) = 1,206.03 1,500.00
Total Claims admitted (Including Interest and penal
Interest) =
2. Unlisted debt securities i.e. NCDs and NCRPS
A. Total amount outstanding as on date (i.e. June 30, 2026)
B. Of the total amount outstanding, amount of default as on
date (i.e. June 30, 2026)
3. Total financial indebtedness of the listed entity 1,206.03 1,500.00
including short-term and long-term debt
The Hon’ble National Company Law Tribunal, Mumbai Bench (“NCLT”), vide order dated
22 February 2023 (“Admission Order”), initiated the Corporate Insolvency Resolution Process
(“CIRP”) of Siti Network Limited (“Siti”/ “Corporate Debtor”) under Section 7 of the Insolvency and
Bankruptcy Code, 2016 (“IBC”) and appointed Mr. Rohit Mehra as the Interim Resolution Professional
(“IRP”) of Siti Networks Limited (“Siti”). The Public Announcement in Form A was made on 25
February 2023, inter alia inviting the creditors to submit their claims to the IRP by 8 March 2023.
Ms. Shilpi Asthana, director of Siti, filed a Company Appeal (AT)(Ins)/274/2023 before the Hon’ble
National Company Law Appellate Tribunal, Principal Bench, New Delhi (“NCLAT”) against the
Admission Order (“NCLAT Appeal”). The NCLAT Appeal was listed before the Hon’ble NCLAT,
Principal Bench on 7 March 2023, wherein the Hon’ble NCLAT after hearing the preliminary
arguments issued notice on the Appeal and passed an interim order directing that “in the meantime,
operation of the impugned order shall remain stayed”.
Vide an order dated 10 August 2023, the Hon’ble NCLAT has dismissed the NCLAT Appeal, along
with all interim applications (“NCLAT Final Order”)
A copy of the NCLAT Final Order was received by the IRP on the evening of 14 August 2023 (post
business hours), by downloading from the website of the Hon’ble NCLAT.
With the passing of the NCLAT Final Order, the Admission Order has been upheld, the stay on the
operation of the Admission Order stands vacated and the CIRP of the Corporate Debtor stands
reinstated, with Mr. Rohit Mehra as its IRP. Further, pursuant to Section 17 of the IBC, the powers of
the Board of Directors of the Corporate Debtor are currently suspended and are vested in the IRP.
On 1 October 2024, the Hon’ble NCLT passed its order (“1 October Order”) in I.A. 4844 of 2023 and
held that (i) insolvency commencement date is fixed at 22 February 2023, (ii) the CIRP related activities
should be reckoned from 22 February 2023, (iii) moratorium under Section 14 of the Code was
applicable during the Stay Period, (iv) the transactions and appropriation undertaking during the Stay
Period shall be revered to the accounts of the Corporate Debtor, and (v) the expenses incurred in the
ordinary course of business to keep the Company as a going concern are to be protected. Certain lenders
of the Company had filed appeals against the 1 October Order before the Hon’ble NCLAT. The RP has
filed a limited appeal against the 1 October, 2024 Order for setting aside the observations and findings
against the RP. On 29 October 2024, the Hon’ble NCLAT directed the lenders to keep the amounts
appropriated by them during the Stay Period in a separate interest-bearing account during the pendency
of the appeals. The Hon’ble NCLAT on 31 July 2025 passed its judgment in CA(AT)(INS) No. 1975
of 2024, CA(AT)(INS) No. 1977 of 2024, CA(AT)(INS) No. 1978-1979 of 2024, CA(AT)(INS) No.
2003 of 2024, CA(AT)(INS) No. 2005 of 2024, CA(AT)(INS) No. 2006 of 2024 and CA(AT)(INS) No.
2192 of 2024 dismissing all appeals and directing the financial creditors to remit the amount back to
the corporate debtor along with accrued interest as per order dated 29 October 2024, (para 14) passed
in these appeals, forthwith.
Certain financial creditors have preferred appeals before the Hon’ble Supreme Court against the
judgment of the Hon’ble NCLAT dated 31st July 2025. There is currently a stay granted by the Hon’ble
Supreme Court to the financial creditors from remitting the amounts received by them during the stay
period of the CIRP, and also a direction that no payments shall be made to operational creditors for
liabilities relating to the stay period of the CIRP
The present filing is being made on the basis of the claims received from the financial creditors as on
10th August 2023 and 22nd February 2023. Any further changes or additions pursuant to the outcome
of the appeals before the Hon’ble Supreme Court will be duly incorporated in subsequent filings.
Kindly take the same on record and oblige.
Thanking you,
Yours faithfully,
For Siti Networks Limited
Suresh Kumar
Company Secretary and Compliance Officer
Membership No. ACS 14390