NSEUpdates6 Aug 2026 · 6 Aug 2026, 10:28 pm
Updates
Mangalam Cement Limited · MANGLMCEM
✦ AI SummaryExpansion
Mangalam Cement Limited has informed the Exchange regarding the commissioning of its captive solar power project and the commencement of solar power supply to the Company.
Analysis Scores
Earnings Impact6/10
Growth Catalyst8/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment6/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Mangalam Cement Limited has informed the Exchange regarding 'Update on Commissioning of Captive Solar Power Project and supply of Solar Power to the Company.'.
Attachments (1)
📄pdf
Download →
MANGLMCEM_06082026222809_Intimation_to_Stock_Excahnge_01_06_2026_SOLAR_S.pdf
View document text
MCL/SEC/2026-27
6th August, 2026
The Corporate Relations Department The Corporate Relations Department
The National Stock Exchange of India Ltd. Department of Corporate Services
Exchange Plaza, 5th Floor, BSE Limited
Plot No. C/1, G-Block 25th Floor
Bandra-Kurla Complex Phiroze Jeejeebhoy Towers
Bandra (E), Mumbai 400 051 Dalal Street, Mumbai – 400 001
Security Code : MANGLMCEM Scrip Code: 502157
Sub: Disclosure under Regulation 30 of the SEBI (Listing Obligations and Disclosure
Requirements) Regulations, 2015 – Update on Commissioning of Captive Solar
Power Project and supply of Solar Power to the Company.
Dear Sir/Madam,
This has reference to our earlier intimation dated 5th September, 2024, whereby the Company
had informed the Stock Exchanges regarding the execution of a Power Purchase Agreement
(PPA) and Share Subscription and Shareholders' Agreement (SSSHA) for acquiring a captive
equity stake in Suryadeep RJ-1 Projects Private Limited to procure solar power under the
Captive Open Access model.
Pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements)
Regulations, 2015, we are pleased to inform you that Suryadeep RJ-1 Projects Private Limited
has successfully commissioned its 15.17 MW (AC) / 22 MW (DC) Solar Power Plant located
at Barmer District, Rajasthan, under the Group Captive Generation Mechanism through an
Open Access Solar Photovoltaic (PV) Plant developed on a Build-Own-Operate (BOO) basis.
We further wish to inform you that the Short-Term Open Access (STOA) for evacuation of
power became effective from 6th August, 2026, and the supply of solar power to the Company
has commenced from the same date.
You are requested to take the above information on your records.
Thanking You,
Yours faithfully,
For Mangalam Cement Limited
Pawan Kumar Thakur
Company Secretary & Compliance Officer
Annexure-A
Disclosure of Information pursuant to Regulation 30 of SEBI (LODR) Regulations, 2015
Sl. Particulars Details
1 Name of the Entity Suryadeep RJ-1 Projects Private Limited
2 Nature of Contract/Arrangement Power Purchase Agreement (PPA) under
Captive Open Access
3 Product/Service Involved Solar Power Generation and Supply
4 Date of Original Intimation 5th September, 2024
5 Current Status / Milestone Achieved Short-Term Open Access (STOA) for
evacuation of power became effective
from 6th August, 2026, and the supply of
solar power to the Company has
commenced from the same date.
6 Date of Commissioning 6th August, 2026
7 Expected Financial/Operational Reduction in power costs and increased
Impact share of renewable energy in the total
power mix of the Company.