BSECompany Update6 Aug 2026 · 6 Aug 2026, 04:48 pm
Please find attached the Analyst / Institutional Investor Meeting Presentation.
Hindustan Construction Company Ltd · 500185
✦ AI SummaryResults
Hindustan Construction Company Ltd has released its Q1 FY27 results, showing a standalone turnover of ₹982 Cr and ₹37 Cr net profit. The company has also announced a new order of ₹127 Cr and plans to pre-pay ₹100 crore debt in August 2026.
Analysis Scores
Earnings Impact5/10
Growth Catalyst6/10
Governance Concern2/10
Regulatory Risk1/10
Balance Sheet Risk4/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Hindustan Construction Company Ltd - 500185 - Announcement under Regulation 30 (LODR)-Investor Presentation
Attachments (1)
📄pdf
Download →
92c762b3-42bf-45a9-be07-96f1b700cd98.pdf
View document text
HCC/SEC/AM/2026 August 6, 2026
BSE Limited National Stock Exchange of India Ltd.
The Corporate Relationship Dept, Exchange Plaza,
Phiroze Jeejeebhoy Towers, Bandra-Kurla Complex,
Dalal Street, Bandra (East),
Mumbai-400 001 Mumbai-400 051
Scrip Code : 500185 Symbol: HCC
Dear Sir I Madam,
Sub : Analyst /Institutional Investor Meeting Presentation
Further to our letter dated July 29, 2026, and pursuant to Regulation 30(6) of the SEBI (Listing
Obligations and Disclosure Requirements) Regulations, 2015, we are enclosing a copy of the
presentation to be made before the Analyst & Institutional Investor Meeting, scheduled to be held
on August 6, 2026.
We request you to kindly take the above on record.
Yours sincerely,
For Hindustan Construction Company Ltd.
Nitesh Kumar Jha
Company Secretary
Encl.: As above
Hindustan Construction Co Ltd
Hincon House,
LBS Marg, Vikhroli (West).
Mumbai · 400 083, India
Tel: +91 22 2575 1000 Fax: +91 22 2577 7568
CIN: L45200MH1926PLC001228 www.hccindia.com
Hindustan Construction Co Ltd
Investor/Analyst Presentation
Q1 FY27
Nation building since 1926
60°/o 26°/o
of India's installed of India's installed
nuclear power hydro power
capacity capacity
2 August 6, 2026 Analyst Presentation Q1 FY27
Key performance highlights: Q1 FY27
1. Standalone turnover at ₹982 Cr and ₹37 Cr net profit in Q1 FY27
2. Consolidated PAT improved marginally to ₹51 Cr on revenue of ₹993 Cr
3. EBITDA margin at 10.7% in Q1 FY27 (vs. 14.9% in Q1 FY26)
4. Pre-payment of ₹100 crore debt planned in August 2026 with further pre-payments to follow
5. New order of ₹127 Cr; L1 bids worth ₹2,124 Cr (HCC share : ₹1,671 Cr)
6. 4 bids ~₹9,997 Cr under evaluation (HCC share: ~₹7,747 Cr); ₹85,907 Cr pipeline under pursuit
3 August 6, 2026 Analyst Presentation Q1 FY27
Diversified & robust orderbook
Order Backlog: ₹12,976 Cr
Order Book Position (Business Line Wise) Order Book Position (Geographical)
64% 7%
Uttarakhand Bihar Maharashtra
Transport Hydro Water Nuclear & Buildings Gujarat Manipur Tamil Nadu
Madhya Pradesh Rajasthan Others
4 August 6, 2026 Analyst Presentation Q1 FY27
Operations Update: Indore Metro
TBM deployment advancing, with piling, station excavation and launch preparations progressing
across the corridor.
5 August 6, 2026 Analyst Presentation Q1 FY27
Operations Update: Patna Metro PC 05 & PC 06
Batching Plant Segment Casting
Casting yard development and guide wall works progressed. Segment casting commenced, while TBM
deliveries were scheduled for September–December 2026.
6 August 6, 2026 Analyst Presentation Q1 FY27
Operations Update: Agardanda Creek Bridge
Piling, pier and segment casting works progressed, while land handover and statutory
clearances are expected by Nov 2026.
7 August 6, 2026 Analyst Presentation Q1 FY27
Operations Update: Bhivpuri PSP (3x333.33 MW)
Upper Intake Excavation
Powerhouse Excavation
Earthworks and steel liner fabrication progressed across key project components, with forest and road
clearances pending for road works.
8 August 6, 2026 Analyst Presentation Q1 FY27
Operations Update: Vishnugad Pipalkoti HEP (4x111 MW)
Machine Hall Unit 2 Machine Hall Unit 3 Surge Shaft
Dam Desilting Chamber Tail Race Tunnel
Major civil works progressed across the dam, tunnels and intake structures, with Machine Hall handed
over for Units 1 & 2 and HRT excavation reaching 85%
9 August 6, 2026 Analyst Presentation Q1 FY27
Operations Update: Tapovan Vishnugad HEP (4x130 MW)
Face 5
Breakthrough of Face 2 & Face 3
HRT breakthrough achieved; excavation and overlining progressed across remaining faces.
10 August 6, 2026 Analyst Presentation Q1 FY27
Operations Update: Hindalco PS & PSS
Pot shell prototype approved, with bulk fabrication commenced and superstructure prototype fabrication
in progress.
11 August 6, 2026 Analyst Presentation Q1 FY27
Standalone Financials: Q1 FY27
Q1 FY27 Q1 FY26 y-o-y Q4 FY26
Particular
₹ Cr ₹ Cr % ₹ Cr
Income from operations 981.7 1,069.0 -0.1 988.7
Other income 31.0 20.7 0.5 28.1
Total income 1,012.7 1,089.7 -0.1 1,016.8
Construction cost (incl. material) and other expenses 790.1 826.3 -0.0 722.4
Employees cost 87.1 83.8 0.0 86.1
EBITDA (excluding other income) 104.5 159.0 -0.3 180.3
EBITDA margin (%) (excluding other income) 10.7% 14.9% -4.2% 18.2%
Finance cost 79.8 114.6 -0.3 95.0
Depreciation 5.4 10.4 -0.5 5.6
Profit before exceptional items and tax 50.3 54.7 -0.1 107.8
Exceptional item - Gain/(loss) - - - -35.6
Profit/(loss) before tax 50.3 54.7 -0.1 72.2
Tax expense 13.2 16.2 -0.2 27.6
Profit/(loss) after tax 37.1 38.6 -0.0 44.6
Other comprehensive income/(loss) 10.1 4.0 1.6 -3.9
Total comprehensive income 47.2 42.5 0.1 40.8
12 August 6, 2026 Analyst Presentation Q1 FY27
Consolidated Financials: Q1 FY27
Q1 FY27 Q1 FY26 y-o-y Q4 FY26
Particular
₹ Cr ₹ Cr % ₹ Cr
Income from operations 993.4 1,091.3 (0.1) 992.2
Other income 62.1 27.3 1.3 25.3
Total income 1,055.5 1,118.7 (0.1) 1,017.5
Construction cost (including material) and other expenses 799.4 826.4 (0.0) 731.7
Employees cost 89.4 85.5 0.0 89.7
Share in profit/(loss) of associates and joint venture (net) 0.5 - - 5.7
EBITDA (excluding other income) 105.1 179.5 (0.4) 176.5
EBITDA margin (%) (excluding other income) 10.6% 16.5% -5.9% 17.8%
Finance cost 86.8 121.9 (0.3) 104.7
Depreciation 6.0 11.6 (0.5) 5.2
Profit/(loss) before tax 74.4 73.3 0.0 92.0
Tax expense/(credit) 23.3 22.6 0.0 33.0
Profit/(loss) after tax 51.1 50.7 0.0 58.9
Other comprehensive income/(loss) (1.2) 87.1 (1.0) (2.1)
Total comprehensive income/(loss) (after tax) 49.9 137.9 (0.6) 56.8