Partial restart of the Unit closed due to flooding on 23rd July 2026.
Jai Corp Ltd · 512237
✦ AI SummaryOrder Win
Jai Corp Ltd has partially restarted operations at one of its plastic processing units located at Vasona, which was stopped due to flooding on 23rd July 2026. The company is unable to quantify the impact of this disruption.
Analysis Scores
Earnings Impact5/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk3/10
Liquidity Impact8/10
Market Sentiment6/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Jai Corp Ltd - 512237 - Announcement under Regulation 30 (LODR)-Strikes /Lockouts / Disturbances
Attachments (1)
📄pdf
Download →
a9a23b8e-129f-40bd-a225-3ac0f386844f.pdf
View document text
Jai Corp Limited
Corporate Office: #603, Embassy Centre, Backbay Reclamation, Nariman Point,
Mumbai- 400 021. Tel: 91-22-3521 5146/3139 6050; E-mail: cs@jaicorpindia.com/
E-mail for Investors: cs2@jaicorpindia.com
CIN: L17120MH1985PLC036500 website: www.jaicorpindia.com
July 30, 2026
The Manager Listing Compliances,
BSE Limited.
BSE Scrip Code: 512237
The Manager, Listing Department,
National Stock Exchange of India Limited.
NSE Symbol: JAICORPLTD
Sub: Intimation pursuant to Regulation 30 of SEBI (LODR) Regulation, 2015
Dear Sir/ Madam,
This has reference to our intimation dated 23rd July 2026 regarding the stoppage of
operations of one of the Company's plastic processing Units located at Vasona due to
flooding.
That Unit has partially restarted its operations from 07:00 am (IST) today i.e. 30th July
2026.
At this juncture, we are unable to quantify the impact of this disruption.
Further, the details as required under SEBI (Listing Obligations and Disclosure
Requirements) Regulations, 2015 read with SEBI Master Circular No.
SEBI/HO/49/14/14(7)2025-CFD-POD2/I/3762/2026 dated January 30, 2026, is given
as ‘Annexure- A’ attached to this letter.
Thanking you,
Yours faithfully,
For Jai Corp Limited
Company Secretary
Encl.: As Above.
Regd. Office: A-3, M.I.D.C. Indl. Area, Nanded-431 603, Maharashtra.
Jai Corp Limited
Corporate Office: #603, Embassy Centre, Backbay Reclamation, Nariman Point,
Mumbai- 400 021. Tel: 91-22-3521 5146/3139 6050; E-mail: cs@jaicorpindia.com/
E-mail for Investors: cs2@jaicorpindia.com
CIN: L17120MH1985PLC036500 website: www.jaicorpindia.com
Annexure- A
The details required under Regulation 30 of Listing Regulations read with the SEBI
circular bearing reference number HO/49/14/14(7)2025-CFD-POD2/I/3762/2026
dated January 30, 2026 for disruption of operations of any one or more units or
division of the listed entity due to natural calamity (earthquake, flood, fire etc.),
force majeure or events such as strikes, lockouts etc. are as under:
Sr. No. Particulars
1. Insurance amount claimed and realized The Company is in the
by the listed entity for the loss/damage process of ascertaining
the extent of production
loss/ property damage
caused by disruptions.
2. The actual amount of damage caused Not yet ascertained.
due to the natural calamity or other force
majeure events
3.. Details of steps taken to restore normalcy That Unit has partially
and impact of the natural calamity/ other restarted its operations
force majeure events on production or from 07:00 am (IST)
service, financials or the entity today i.e. 30th July 2026.
For Jai Corp Limited
Company Secretary
Regd. Office: A-3, M.I.D.C. Indl. Area, Nanded-431 603, Maharashtra.