BSECompany Update15h ago · 18 Nov 2026, 05:15 pm
Announcement under Regulation 30 (LODR) - Project Update
Glen Industries Ltd · 544444
✦ AI Summaryproject_update
Glen Industries Ltd has announced a project update under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015. The update covers the status of land conversion, site preparation, regulatory approvals, construction and design, procurement, and timeline for commercial production. The company has utilized the proceeds from its Initial Public Offering (IPO) in accordance with the objects and purposes specified in the Prospectus.
Analysis Scores
Earnings Impact5/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk6/10
Balance Sheet Risk3/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Glen Industries Ltd - 544444 - Announcement Under Regulation 30 (LODR) - Project Update
Attachments (1)
📄pdf
Download →
3c0fc784-7294-4dd3-96a6-867f378a2316.pdf
View document text
November 18, 2026
BSE Ltd
P J Towers, Dalal Street
Mumbai – 400001
Symbol: GLEN, ISIN: INE0UMC01019, Series – EQ
Subject: Project update dated October 28, 2026.
Dear Sir/Madam,
Pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations,
2015, we hereby enclose the Project Update dated October 28, 2026, in the meeting of the Board of the
Directors held on November 13, 2026.
The aforesaid Project Update is enclosed herewith for information of the Exchange and the stakeholders.
This is for information and records.
Thanking you,
Yours faithfully,
For Glen Industries Limited
Shikha Sureka
Company Secretary and Compliance officer
Project Update
• Land Conversion: Conversion of land use from agricultural to industrial has been
successfully completed.
• Site Preparation: Land filling work has been completed.
• Regulatory Approvals:
1. No Objection Certificate / Consent to Establish (CTE) obtained from the West Bengal
Pollution Control Board.
2. Fire NOC / Fire Safety Report (FSR) received from the West Bengal Fire & Emergency
Services.
3. WBSEDCL electricity final sanction letter for sanction of power has been received.
Agreement for electricity is being executed.
4. Building Plan sanction has been received from Zila Parishad.
With this, all regulatory approvals are in place to execute implementation of the project.
• Construction & Design:
1. Contract for the Pre-Engineered Building (PEB) structure has been awarded and erection
work has commenced.
2. Piling work has been completed and foundation work will most likely be completed by
end of October, 2026. The delay has been caused due to excessive rain.
• Procurement:
1. Orders for all plant and machineries has been placed.
2. Order for utility equipment has been placed.
• Timeline:
As disclosed in the Company’s Red Herring Prospectus, commercial production was
originally expected to commence by Q4 of FY 2025–26 which was later extended to Q3 of
FY 2026-27
However, due to the below delay in regulatory approvals and excessive rain in West Bengal,
the commencement of commercial production has been extended and is now expected to
commence by Q4 of FY 2026–27.
The reasons for delay are mainly the following:
1. SIR and election in West Bengal have caused huge delay in the building plan
approval. Even post elections the building plan sanctioning is delayed due to non-
functioning of Zila Parishad and finally received in July 2026.
2. Excessive rain has delayed the piling and foundation work post receipt of Building
Plan approval.
3. Delay in sanctioning of power to the project due to SIR and election process.
All these factors were beyond the control of the company.
Utilization of IPO Proceeds
The Company has fully utilized the proceeds raised through its Initial Public Offering (IPO) in
accordance with the objects and purposes specified in the Prospectus. The utilization of IPO
proceeds is in line with the commitments made to the investors, and no unutilized IPO proceeds
remain as on date.