BSECompany Update18h ago · 18 Nov 2026, 01:29 pm
Material litigation under Regulation 30(4) of the Securities Exchange Board of India (Listing Obligations and Disclosure Requirements) Regulations, 2015 ('Listing Regulations') - Update
JSW Energy Ltd · 533148
✦ AI SummaryLitigation
JSW Energy Ltd has informed that the Hon'ble Appellate Tribunal for Electricity (APTEL) has allowed the appeal and set aside the Andhra Pradesh Electricity Regulatory Commission (APERC) order, directing the AP Discoms to pay for energy generated by the wind power generators at the applicable generic tariff, irrespective of whether the actual generation exceeds the normative Capacity Utilization Factor (CUF), together with applicable interest in accordance with the respective Power Purchase Agreements.
Analysis Scores
Earnings Impact5/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk8/10
Balance Sheet Risk1/10
Liquidity Impact6/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
JSW Energy Ltd - 533148 - Material Litigation Under Regulation 30(4) Of The Securities Exchange Board Of India (Listing Obligations And Disclosure Requirements) Regulations, 2015 ('Listing Regulations') - Update
Attachments (1)
📄pdf
Download →
a2ba6090-f772-4b7d-a1d6-9721abc5905c.pdf
View document text
Energy Limited
Regd. Office: JSW Centre,
Bandra Kurla Complex,
Bandra (East), Mumbai – 400 051,
CIN: L74999MH1994PLC077041
Phone: 022-4286 1000
Fax: 022-4286 3000
Website: www.jsw.in
SEC / JSWEL
18th November 2026
BSE Limited National Stock Exchange of India Limited
Phiroze Jeejeebhoy Towers Exchange Plaza
Dalal Street Bandra Kurla Complex, Bandra (E)
Mumbai - 400 001 Mumbai - 400 051
Scrip Code: 533148 Symbol: JSWENERGY
Sub: Material litigation under Regulation 30(4) of the Securities Exchange Board of India
(Listing Obligations and Disclosure Requirements) Regulations, 2015 (“Listing
Regulations”) - Update
Ref: Regulation 30 of the Listing Regulations
Dear Madam / Sir,
We refer to our earlier disclosure dated 30th September 2023. Our subsidiaries namely JSW Vayu
(Tungabhadra) Private Limited, JSW Vayu (Indravati) Private Limited, JSW Wind Power (Pennar)
Private Limited and JSW Wind Power Limited had filed appeal before the Hon’ble Appellate
Tribunal for Electricity (“APTEL”) against the Andhra Pradesh Electricity Regulatory Commission
(“APERC”) order dated 18th October 2023 which directed AP Discom to pay Rs. 0.50 per unit for
energy supplied beyond the prescribed Capacity Utilization Factor (“CUF”).
We wish to inform you that APTEL, vide its order dated 17th November 2026, has allowed the
appeal and set aside the APERC order. APTEL has directed the AP Discoms to pay for energy
generated by the wind power generators at the applicable generic tariff, irrespective of whether
the actual generation exceeds the normative CUF, together with applicable interest in accordance
with the respective Power Purchase Agreements.