BSECompany Update12 Nov 2026 · 12 Nov 2026, 12:02 pm
Transcript of Earnings Conference Call - H1 & FY27.
B.R.Goyal Infrastructure Ltd · 544335
✦ AI SummaryResults
B.R.Goyal Infrastructure Ltd announced its H1 FY27 earnings conference call transcript, highlighting key business developments and secured orders worth INR1,087 crores during the period.
Analysis Scores
Earnings Impact5/10
Growth Catalyst6/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
B.R.Goyal Infrastructure Ltd - 544335 - Announcement under Regulation 30 (LODR)-Earnings Call Transcript
Attachments (1)
📄pdf
Download →
f63f64db-5bce-4512-83ec-18bd8d46f8d3.pdf
View document text
B.R.Goyal Infrastructure Limited
CIN: L04520MP2005PLC017479
Date: 12 November 2026
Corporate Relations Department
BSE Limited
Phiroze Jeejeebhoy Towers,
Dalal Street,
Mumbai – 400 001
Scrip Code: 544335 | Scrip Symbol: BRGIL | ISIN: INE00ST01011
Subject: Transcript of Earnings Conference Call – H1 & FY27
Reference: Intimation pursuant to Regulation 30 of the Securities and Exchange Board of India (Listing
Obligations and Disclosure Requirements) Regulations, 2015
Dear Sir/ Madam,
In terms of Regulations 30 and 46 read with clause 15 of Para A of Part A of Schedule III of the SEBI (Listing
Obligations and Disclosure Requirements) Regulations, 2015, please find enclosed the transcript of the
earnings conference call for the half-year ended 30 September 2026, conducted on 06 November 2026, for
your information and record.
This intimation is also available on the website of the Company at the web link:
https://brginfra.com/page/investor.
We request you to take the above information on record and acknowledge the receipt.
Thanking you,
Yours faithfully,
For, B.R.Goyal Infrastructure Limited
Ritika Jhala
Company Secretary and Compliance Officer
M. No.: A73846
Encl.: As above
Regd. Off.: 3-A, Agrawal Nagar, Indore – 452 001, Madhya Pradesh, INDIA
Tel.: (+91-731) 2403831 | Email: enquiry@brginfra.com | Website: www.brginfra.com
“B. R. Goyal Infrastructure Limited
H1 FY27 Earnings Conference Call”
November 06, 2026
MANAGEMENT: MR. YASH GOYAL – EXECUTIVE DIRECTOR – B. R.
GOYAL INFRASTRUCTURE LIMITED
MR. DASHARATH TOMAR – CHIEF FINANCIAL
OFFICER – B. R. GOYAL INFRASTRUCTURE LIMITED
MODERATOR: MR. SMIT PATEL – ADFACTORS PR
Page 1 of 13
B. R. Goyal Infrastructure Limited
November 06, 2026
Moderator: Ladies and gentlemen, good day and welcome to the H1 FY27 Earnings Conference Call, hosted
by B.R.Goyal Infrastructure Limited. As a reminder, all participant lines will be in the listen-
only mode and there will be an opportunity for you to ask questions after the presentation
concludes. Should you need assistance during the conference call, please signal for an
Moderator: by pressing star and then zero on your touchtone phone.
I now hand the conference over to Mr. Smit Patel from Adfactors PR. Thank you, and over to
you, sir.
Smit Patel: Hello, good morning, everyone. Thank you for joining us on H1 FY27 earnings conference call
of B.R.Goyal Infrastructure Limited. Today we have with us Mr. Yash Goyal, Executive
Director, and Mr. Dasharath Tomar, Chief Financial Officer, who will take you through
company's operational and financial performance for the half year ended 30th September 2026.
Before we begin, I would like to remind everyone that certain statements made during today's
discussions may be forward-looking in nature and may involve risks and uncertainties. A
detailed statement in this regard is available in H1 FY27 results presentation uploaded on the
stock exchange and on the company's website.
I now hand over the call to Mr. Yash Goyal to begin the proceedings. Thank you, and over to
you, sir.
Yash Goyal: Thank you so much, sir. Good morning, everyone, and welcome to B.R. Goyal Infrastructure
Limited's earning conference call to discuss our performance for the half year ended September
30, 2026.
I would like to thank our shareholders, investors, analysts, and all other stakeholders for joining
us today for their continued interest and support. I will begin with a brief overview of the
company and the key business developments for H1 FY27.
B.R.Goyal Infrastructure Limited is a diversified infrastructure company with more than two
decades of experience in executing projects across roads, highways, bridges, buildings, and
urban infrastructure. Over the years, we have expanded beyond our core EPC operations into
complementary businesses including toll collection contracts, ready-mix concrete, and
residential plotting projects.
We have also entered the wastewater treatment and underground sewage infrastructure
segments, further broadening our presence across the infrastructure sector. Our execution
capabilities are supported by experienced team, a fleet of construction equipment’s and vehicles,
and established relationship with central and state government departments, public sector
undertakings, and infrastructure authorities. Our clients include the National Highway Authority
of India, State Public Work Departments, Municipal Corporations, Urban Development
Authorities, and other government agencies.
During H1 FY27, we continue to expand our project portfolios, securing orders across road
infrastructure, civil construction, toll collection, including operation and maintenance. During
Page 2 of 13
B. R. Goyal Infrastructure Limited
November 06, 2026
the period H1 FY27, the company secured fresh work orders aggregating approximately
INR1,087 crores on a gross basis. A key win was the Bundelkhand Expressway user fee toll
collection and O&M contract from UPEIDA valued for INR377.54 crores for two years period.
We also secured civil and structure work for Cyber City for Sneh Developers, Micro Mitti
Group, valued at INR81.75 crores with a construction period of 24 months, plus three months
grace period. In addition, we received civil contracts from LNJ Greenpet for its Ratlam project
valued at INR13 crores plus GST with a completion period of six months.
We also secured six, fresh toll plazas from NHAI. These include Katpur in Gujarat valued at
INR118 crore; Husnapur in Maharashtra, valued at INR39 crore; Jajau in Madhya Pradesh,
valued at INR151 crores; Surapattu in Tamil Nadu, valued at INR119 crores; Chillakallu in
Telangana, valued at INR108 crores, and Khambara in Maharashtra, valued at INR52 crores.
These inflows reflect our continued focus on pursuing opportunities across our core
infrastructure and toll collection businesses.
As on September 30, 2026, our order book stood at INR1,755 crores. It comprises road projects
of INR589 crores, building projects of INR72 crores, wastewater work of INR132 crores, toll
collection contracts of nearly INR962 crores. This diversified book together with our bidding
pipeline, various revenue visibility across multiple businesses, segments, and support for growth
plans.
Looking ahead, our priorities remain strengthening, execution, improving operational efficiency,
pursuing opportunities across roads, buildings, wastewater, and toll collection. We will continue
to evaluate larger EPC opportunities and potential PPP projects selectively, while maintaining a
disciplined approach to project selection and growth.
Now with this, I would like to hand over the call to our Chief Financial Officer, Mr. Dasharath
Tomar, who will take you through our financials and operation performance of H1 FY27. Over
to you, sir.
Dasharath Tomar: Thank you, Yash. Good morning, everyone. I will now take you through company's financial
and operational performance for the half-year ended September 30, 2026. For H1 FY27, revenue
from operation stood around INR550 crore, compared with last, last H126 revenue was INR342
crore, representing year-on-year growth around 61%. Performance was supported by execution
across and EPC projects along with the contributions from and toll collection contracts.
EBITA excluding other income excluded were INR35 crores, compared with INR27 crores in
the last corresponding period last year, representing growth of around 28%. EBITDA margin
was at 6.38% in H1 FY26. We remained focus on disciplined project execution, cost control,
and improving operating efficiency across our business segments. Profit after tax for H1 FY27
stood at around INR22 crores, compared with INR16 crores in H1 FY26, representing year-on-
year growth of around 38%. PAT margin was at 4.02% in H1 FY27.
From an operational perspective, the addition of new toll collection contracts and construction
orders has further expanded our project portfolio across EPC and toll collection contracts. Going