BSECompany Update3 Nov 2026 · 3 Nov 2026, 07:11 pm
Investor Presentation Q2 & H1 FY27
H.G. Infra Engineering Ltd · 541019
✦ AI SummaryResults
H.G. Infra Engineering Ltd has released its Q2 and H1 FY27 investor presentation, highlighting its operational and order book performance, as well as significant events and updates on new projects.
Analysis Scores
Earnings Impact6/10
Growth Catalyst4/10
Governance Concern2/10
Regulatory Risk1/10
Balance Sheet Risk3/10
Liquidity Impact7/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
H.G. Infra Engineering Ltd - 541019 - Announcement under Regulation 30 (LODR)-Investor Presentation
Attachments (1)
📄pdf
Download →
3dd9606a-d764-44d1-aa7a-a7d44e79ccb6.pdf
View document text
HGIEL/HO/COMPLIANCE/2026-27/721 November 03, 2026
BSE Limited National Stock Exchange of India Limited
Phiroze Jeejeebhoy Towers, Exchange Plaza, C-1, Block G,
Dalal Street, Bandra Kurla Complex, Bandra (East),
Mumbai- 400 001 Mumbai- 400 051
Scrip Code: 541019/977063 Scrip Symbol- HGINFRA
Dear Sir/Madam,
Sub: Investor Presentation Q2 & H1 FY27
Kindly find enclosed a copy of the Investor Presentation on the Unaudited Standalone and Consolidated
Financial Results of the Company for the quarter and half year ended September 30, 2026.
The above information is also being uploaded on the Company’s website at: https://www.hginfra.com
This is for your information and records.
Thanking you,
Yours faithfully,
For H.G. Infra Engineering Limited
Ankita Mehra
Company Secretary & Compliance Officer
Mem. No.: A33288
Encl.: As above
H.G. INFRA
ENGINEERING LTD.
Building Highways, Connecting Destinations
Celebrating 24 Years of Trust, Passion and Quality
Investor Presentation –
Q2FY27 & H1FY27
HG Infra :
Redefining India’s Infrastructure
BUILDING BLOCKS OF H.G
FiveBUSINESS SEGMENTS
17.5% 11.9%
ROADS &
14 Revenue CAGR EBITDA CAGR
HIGHWAYS
(FY 21-26) (FY 21-26)
STATES
PAN India Presence
across
13.0% Rs. 13,685
RAILWAY &
METRO 36+ PAT CAGR Crore
(FY 21-26)
ORDER BOOK
ACTIVE PROJECTS
(AS OF Sept,26)
SOLAR 2900+
BESS & T&D
MODERN FLEET SOLAR PLANTS
PROJECTS
EQUIPMENT (Considered as 1
Project in OB)
4400+
BESS
19 10
EMPLOYEES
ROAD RAILWAY
PROJECTS PROJECTS
TRANSMISSION
DISTRIBUTION
H.G Infra Engineering Ltd; Q2FY27-Investor Presentation 2
Operational &
Orderbook Highlights
Order Book as of Sept 2026
Sector Order Book (Rs MN) % State No of Projects % Share
Road 87,921 64% Himachal Pradesh 1 0.1%
Railway 28,833 21% Uttar Pradesh 5 10.2%
Transmission 14,001 10% Maharashtra 5 35.1%
BESS 5,026 4% Bihar 1 2.1%
Solar 1,068 1% Delhi 3 5.5%
Madhya Pradesh 1 2.4%
Total 1,36,849 100%
Rajasthan 1 0.8%
Sector Type Order Book (Rs MN) %
Gujarat 4 6.6%
EPC 95,234 70%
Odisha 4 12.4%
HAM-Road 41,615 30%
Jharkhand 4 19.6%
Total 1,36,849 100%
Telangana 2 0.1%
Sector Type Order Book (Rs MN) % Andhra Pradesh 2 1.6%
Govt. 88,440 65% Haryana 2 2.0%
Karnataka 1 1.5%
Private 48,409 35%
Total 36 100%
Total 1,36,849 100%
H.G Infra Engineering Ltd; Q2FY27-Investor Presentation
Significant Events and update on New Projects till Sept,2026
L1 DECLARED :
Client Mode Project Name LOA Date
Mirzapur Thermal Energy, UP Railway Mirzapur Thermal 14.04.2026
Welspun Enterprises Ltd Road Pune-Shirur (Welspun) 11.05.2026
REC Power Development and Consultancy
Transmission WR-ER Part-C (T&D) 12.06.2026
Limited
REC Power Development and Consultancy
Transmission Ranipur - Chunar (T&D) 18.08.2026
Limited
Department of Skill, Employment &
L&D ITI Upgradation – Bhiwadi Cluster (L&D) 14.08.2026
Entrepreneurship, Government of Rajasthan
DECLARATION OF APPOINTED DATE :
Client State Appointed Date
Construction of 6lane Greenfield Varanasi Ranchi Kolkata Highway from Deoria village to Donoreshan
(Jharkhand P-10) village from km 253.000 to km 288.600 under Bharatmala Pariyojana in the State of Jharkhand on 30-05-2026
HAM (PKG 10)
H.G Infra Engineering Ltd; Q2FY27-Investor Presentation 5
Significant Events and update on New Projects till Q2FY27
CONTRACT AGREEMENT SIGNING :
Sr. No. Project Name Agreement Signed on
1 OD-3 (CRRR) Govindpur-Tangi 24-04-2026
2 WR-ER Part-C (T&D) 30-06-2026
3 Ranipur - Chunar (T&D) 26-09-2026
4 ITI Upgradation – Bhiwadi Cluster (L&D) 07-09-2026
COMPLETION CERTIFICATE :
Sr. No. Project Name Agreement Signed on
Development of 6-lane Urban Extension Road (UER) –2 – NH-344 M, Package 1 (from NH 1 to Karala-Kanjhawala road, w.e.f. 28.02.2025
UER –2
Km -0+700 to 15+000) in the State of Delhi Ltr. no, 1536 dt 23-09-2026
PROVISIONAL COMPLETION CERTIFICATE :
Sr. No. Project Name Agreement Signed on
Execution of Civil & Associated works on Engineering Procurement & Construction (EPC) basis of Development of
Ganga an Access-Controlled Six lane (Expandable to Eight lane) Greenfield ‘Ganga Expressway’[Group-II, from Km. PCOD w.e.f., 30.04.2026
Expressway 137+600 (Village: Nagla Barah, Distt: Budaun) to Km. 289+300, (Village: UbariyaKhurd, Distt: Hardoi), Design ARTL/1909 dt. 30.05.2026
length=151.700 Km] in the State of Uttar Pradesh on DBFOT (Toll) basis under PPP
H.G Infra Engineering Ltd; Q2FY27-Investor Presentation 6
Update on HAM
Projects
Expanding HAM Projects
All figures in INR Million
Expanding order book , equity commitment comfortably met
Invested Total Debt as of
Awarding Kms Grant
Project State BPC Equity till Sanctioned September
Authority Lane Amount
September 26 Debt 2026
Andhra
Raipur Visakhapatnam AP-1* NHAI 31.77 10,601 4,240 1,687 4,379 4,153
Pradesh
Karnal Ringroad NHAI Haryana 34.5 9,971 3,988 1,574 4,650 4,481
Varanasi Kolkata Pkg-10 NHAI Jharkhand 35.6 13,031 5,212 807 6,200 1,541
Varanasi Kolkata Pkg-13 NHAI Jharkhand 28.7 9,251 3,700 718 4,470 1,355
Andhra
Chennai Tirupati II ** NHAI 37.43 8,167 3,267 1,154 4,043 2,100
Pradesh
Uttar
84 Kosi Parikrama MoRTH 63.84 7,631 3,052 714 3,900 963
Pradesh
Narol Sarkhej MoRTH Gujarat 10.63 7,811 3,124 1,027 4,050 1,611
GobindpurTangi NHAI Odisha 40.33 15,821 6,328 25 8,200 -
Total 7,706 39,892 16,204
*BPC including GST
** after BPC descope of Rs 454.3 Mn and Debt reduction of Rs. 306.8 Mn
*** AP1 Debt surrender of Rs. 141.1 Mn
H.G Infra Engineering Ltd; Q2FY27-Investor Presentation 8
Financial
Highlights
Standalone Highlights – Q2 & H1FY27
All figures in INR Million
Revenue EBITDA PAT
12.7% 11.9% 5.8% 3.6%
11,537
Q2FY27
8,832
1,466
1,047 673
Q2FY26 Q2FY27 Q2FY26 Q2FY27 Q2FY26 Q2FY27
6.7% 3.4%
13.4% 10.2%
H1FY27 28,630 1,928
17,905 3,822
1,817 604
H1FY26 H1FY27 H1FY26 H1FY27 H1FY26 H1FY27
Standalone Basis
H.G Infra Engineering Ltd; Q2FY27-Investor Presentation 10
Consolidated Highlights – Q2 & H1FY27
All figures in INR Million
Revenue EBITDA PAT
22.8% 25.6% 5.7% 8.2%
21,0%
2,495
Q2FY27 9,045 9,736 2,062 53.9%
Q2FY26 Q2FY27 Q2FY26 Q2FY27 Q2FY26 Q2FY27
61.63%% 1.7%
19.5% 26.7%
18.8%
H1FY27
5,533
23,867 4,659
20,742
-76.7%
1,511
H1FY26 H1FY27 H1FY26 H1FY27 H1FY26 H1FY27
Consolidated Basis
H.G Infra Engineering Ltd; Q2FY27-Investor Presentation 11
Standalone profit & loss statement
All figures in ₹ Million
Particulars Q2 FY27 Q2 FY26 YoY H1FY27 H1FY26 YoY
Revenue from Operations 8,832.19 11,537.47 -23.4% 17,904.55 28,629.90 -37.5%
Cost of material consumed 2,813.53 4,250.82 6,785.56 12,208.34
Contract and site expenses 3,866.51 4,757.12 7,060.96 10,277.36
Employee expenses 878.85 863.12 1,811.87 1,792.37
Other expenses 226.04 200.76 428.74 529.51
Total Operating expenses 7,784.93 10,071.82 16,087.13 24,807.58
EBITDA 1,047.26 1,465.65 -28.5% 1,817.42 3,822.32 -52.5%
EBITDA Margin % 11.9% 12.7% 10.2% 13.4%
Finance Cost 508.79 393.11 938.24 769.58
Depreciation 327.36 340.34 632.33 669.53
Other Income 249.26 165.68 278.27 188.44
Exceptional Item* -21.23 - 279.89 -
PBT 439.14 897.88 -51.1% 805.01 2,571.65 -68.7%
PBT Margin % 5.0% 7.8% 4.5% 9.0%
Tax expenses (Credit) 117.83 224.82 200.98 643.90
PAT 321.31 673.06 -52.3% 604.03 1,927.75 -68.7%
PAT Margin % 3.6% 5.8% 3.4% 6.7%
Other Comprehensive Income -4.89 -3.36 -10.43 -5.77
Total Comprehensive Income 316.42 669.70 593.60 1,921.98
H.G Infra Engineering Ltd; Q2FY27 -Investor Presentation 12
Consolidated profit & loss statement
All figures in ₹ Million
Particulars Q2 FY27 Q2 FY26 YoY H1FY27 H1FY26 YoY
Revenue from Operations 9,735.87 9,045.03 7.6% 20,741.72 23,867.05 -13.1%
Cost of material consumed 2,558.73 3,176.98 6,369.77 9,511.18
Contract and site expenses 3,579.02 2,725.82 6,570.39 7,332.34
Employee expenses 853.23 846.79 1,787.72 1,759.81
Other expenses 249.63 233.11 480.56 604.99
Total Operating Expenses 7,240.61 6,982.70 15,208.44 19,208.32
EBITDA 2,495.26 2,062.33 21.0% 5,533.28 4,658.73 18.8%
EBITDA Margin % 25.6% 22.8% 26.7% 19.5%
Finance Cost 1,160.51 1,081.10 2,336.70 2,026.32
Depreciation 526.26 400.46 976.66 756.69
Other Income 238.81 134.76 293.47 158.20
PBT(Profit before share of