PNC Infratech Limited has informed the Exchange about the transcript of Q2 H1FY27 Earnings Conference Call on Financial Results for the quarter and half year ended September 30, 2026.
Analysis Scores
Earnings Impact5/10
Growth Catalyst6/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment6/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
PNC Infratech Limited has informed the Exchange about Transcript
Attachments (1)
📄pdf
Download →
PNCINFRA_03112026192332_conferencecall3112026.pdf
View document text
PNC lnfratech Limited
An ISO 9001 :2015 Certified Company
Ref No: PNC/SE/77 126-27 Date:3.11.2026
To, To,
The Manager The Manager
Deparlment of Corporate Servicos Listing Department
BSE Limited National Stock Exchange of India Limited
Floor 25,P.J. Towers, Exclrange Plaza, BandraKurla Complex,
Dalal Street, Mumbai - 400 001 Bandra (E), Munrbai - 400 051
Scrip code:539150 NSE Symbol: PNCINFRA
Dear Sir,
Sub- Transcript of Q2 H1FY27 Earnings Confcrcncc Call on Financial llesults for the
quarter and half year cnded September 3{l,2ll2(t
Pursuant to Regulation 30 of the SEBI (Listing Obligutiuns antl l)isolosurc Requirements)
Regulations, 2015 we are enclosing herewith the transoript ol'ln r:arnirrgs confbrence call on
Financial Results for the quarter and half year ended Soptcnrbor 30.2026 hclcl on Thursday, 29th
October,2026.
You are requested to take this information on your recorcl.
Thanking you,
Yours faithfully,
For PNC Infratech Limited
Tapan Jain
Company Secretary & Compliance Officer
ICSI M. No.: 422603
Encl: a/a
Corporate Office : PNC Tower, Tel. : 91-562-4054400 (30 Lines) Fax:91-562-4070011 Email:ho@pncinfratech.com
3122-D, Civil Lines, Bypass Road, 91-562-4070000 (30 Lines)
FlSFIiIlFl NH-2, Agra-282002
Regd. Office : NBCC Plaza, Tower ll, fel. : 91 -1 1 -29574800 (1 0 Lines) Fax : +91-11-29563844 Email : delhioffice@pncinfratech.com
4th Floor, Pushp Vihar, Sector-V Saket 9'i-11-2956651 1, 64724122 Web. : www.pncinfratech.com
New Delhi:'l'1 001 7 (lndia) CIN :145201D11999P1C195937
“PNC Infratech Limited
Q2 FY27 Earnings Conference Call”
October 29, 2026
E&OE - This transcript is edited for factual errors. In case of discrepancy, the audio
recordings uploaded on the stock exchanges on 29th October 2026 will prevail.
MANAGEMENT: MR. YOGESH JAIN – MANAGING DIRECTOR – PNC
INFRATECH LIMITED
MR. T.R. RAO – DIRECTOR, INFRA – PNC INFRATECH
LIMITED
MR. PANKAJ AGARWAL – VICE PRESIDENT, FINANCE
AND ACCOUNTS – PNC INFRATECH LIMITED
STRATEGIC GROWTH ADVISORS – INVESTOR
RELATIONS – PNC INFRATECH LIMITED
MODERATOR: MR. VAIBHAV SHAH – JM FINANCIAL INSTITUTIONAL
SECURITIES LIMITED
Page 1 of 20
PNC Infratech Limited
October 29, 2026
Moderator: Ladies and gentlemen, good day, and welcome to PNC Infratech Limited Q2 FY27 Earnings
Conference Call, hosted by JM Financial Institutional Securities Limited. As a reminder, all
participants' line will be in the listen-only mode and there will be an opportunity for you to ask
questions after the presentation concludes. Should you need assistance during this conference
call, please signal an operator by pressing star, then zero on your touch-tone phone. Please note
that this conference is being recorded.
I now hand the conference over to Mr. Vaibhav Shah from JM Financial Institutional Securities
Limited. Thank you, and over to you, sir.
Vaibhav Shah: Yes, thank you. Good afternoon, ladies and gentlemen. On behalf of JM Financial, I am pleased
to welcome you all on PNC Infratech Limited second quarter FY27 earnings conference call.
We have with us from the management the Managing Director of the company, Mr. Yogesh
Jain; Mr. T.R. Rao, Director Infra; and Mr. Pankaj Agarwal, Vice President, Finance and
Accounts. We will begin with the opening remarks from the management followed by a Q&A
session. Thank you, and over to you, sir.
Yogesh Jain: Good afternoon, everyone. On behalf of PNC Infratech Limited, I extend a very warm welcome
to everyone for joining us today on this call.
Today, I have with me Mr. T. R. Rao, Director (Infra), Mr. Pankaj Agarwal, Vice President,
Finance and Accounts and Strategic Growth Advisors - our Investor Relations Advisors.
The financial results and investor presentation have been uploaded on the Stock Exchanges and
the Company’s website for your reference.
I would first like to share the key developments in the industry, followed by key operational
updates of the Company and highlights of financial performance during the quarter and half year
ended 30th September 2026, post which, we will be happy to answer your questions.
✓ The highways sector started showing signs of recovery in Q2 of FY27 after significant
slowing down in project awarding activity persisted over the past two years.
✓ During Q2 of FY27, NHAI awarded highway projects of approximately 230 route
kilometers, compared to 107 route kilometers awarded in Q1 of FY27.
✓ Out of the 54 projects identified by NHAI for awarding during the remaining period
of FY27, 19 projects have received approval, while another 17 have been appraised
and balance projects are expected to receive approvals shortly.
✓ It is expected that the pace of awarding would further improve going forward,
supported by healthy pipeline of projects.
✓ As the government is considering development of approximately 51,000 kilometers of
high-speed corridors across the country over the next decade, a large number of new
business opportunities are expected to emerge for highway developers.
✓ Apart from highway sector, significant opportunities are emerging across other
sectors.
✓ Continued Government focus on railways, metro rail, freight corridors, power
transmission, renewable energy & storage, mining, water resources development
Page 2 of 20
PNC Infratech Limited
October 29, 2026
including drinking water supply and urban development, provides sustained growth
opportunities for well-established infra companies.
✓ Railway sector continues to offer a robust pipeline of new projects, supported by the
government's focus on capacity expansion, freight connectivity and logistics
efficiency.
✓ The government has already identified 514 new railway infrastructure projects
spanning approximately 40,000 kilometers, with a total estimated investment of over
₹8.0 lakh crore under the National Rail Plan and Vision 2030, underscoring
significant, large-scale opportunities in the sector.
✓ The proposed HAM-based model for new railway projects, built on the success of
highway development, is also expected to create expanded opportunities for
established highway infrastructure players.
✓ Driven by India’s rapid solar expansion, which reached over 170 GW capacity as of
September 2026 following over 20 GW addition in H1 FY27, the surging demand for
complementary transmission networks and battery energy storage systems is
unlocking significant medium to long-term investment opportunities across the
renewable ecosystem.
✓ The projected capital expenditure of ₹6.0 lakh crore over the next five years in power
transmission sector is aimed at evacuating over 900 GW of non-fossil capacity is
expected to provide robust opportunities in both short and long terms for infra
developers.
✓ While highways will continue to remain our core focus sector, we are actively
expanding into other core sectors to build a broader, more resilient order book that
supports long-term sustainable growth.
✓ Rising crude oil prices on account of the West Asia conflict have increased costs for
key inputs including diesel and bitumen, straining procurement, transport,
construction, and equipment operations severely.
✓ Though MoRTH, NHAI and AAI have extended the monthly price-adjustment
escalation mechanism for eligible EPC and HAM projects through December 31,
2026, the actual impact of financial mitigation is effective only to a limited extent.
✓ Consequently, persistent input cost inflation and partial escalation coverage continue
to exert pressure on the operating margins of infrastructure players.
Now coming to the recent updates on the company:
✓ On October 12, 2026, the Hon’ble Delhi High Court granted a stay on the effect of the
debarment orders issued by the NHAI against both the Company and the
Concessionaire, Awadh Expressway Pvt Ltd. Accordingly, the Company is in a
position to submit bids to all the government authorities including NHAI, MoRTH
and NHIDCL.
✓ In July 2026, Company received the Letter of Award from the Airports Authority of
India for EPC work of Pantnagar Airport in Uttarakhand.
✓ The contract va