NSEUpdates2 Nov 2026 · 2 Nov 2026, 11:33 am
Updates
Borana Weaves Limited · BORANA
✦ AI SummaryRegulatory
Borana Weaves Limited has informed the Exchange about the further delay in commissioning of the 9.9 MW Hybrid Power Project due to factors beyond its control, including high wind speeds and heavy monsoon conditions.
Analysis Scores
Earnings Impact5/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk1/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Borana Weaves Limited has informed the Exchange regarding 'Update on Further Delay in Commissioning of the 9.9 MW Hybrid Power Project'.
Attachments (1)
📄pdf
Download →
BORANA_02112026112424_Reg_30_Update_in_Hybrid_Project.pdf
View document text
Date: 02-11-2026
To, To,
BSE Limited National Stock Exchange of India Limited
P. J. Towers, Dalal Street, Exchange Plaza, Bandra Kurla Complex,
Fort, Mumbai - 400001 Bandra East, Mumbai - 400051
NSE Symbol: BORANA
Scrip Code: 544404
Sub: Intimation pursuant to Regulation 30 of SEBI (Listing Obligations and Disclosure
Requirements) Regulations, 2015 - Further Delay in Commissioning of the 9.9 MW Hybrid
Power Project
Dear Sir/Madam,
This is in continuation of the Company's earlier intimation dated September 30, 2026, regarding
the delay in commissioning of the 9.9 MW Hybrid Power Project at Kalikanagar, Gujarat.
As per the latest communication received from Clean Max Enviro Energy Solutions Limited, the
project developer, the commissioning schedule has been further revised. The first WTG location
along with the 7.65 MW solar component is now tentatively expected to be commissioned
before November 30, 2026, the second WTG location by December 31, 2026, and the third WTG
location by March 31, 2027.
The further delay is due to factors beyond the control of the Company/project developer,
including high wind speeds, heavy monsoon conditions resulting in additional logistics-road
work, and delays in obtaining the required shutdowns of existing 33 kV and 11 kV lines for the
33 kV transmission-line work.
Kindly take the same on record.
Thanking you,
Yours faithfully,
For Borana Weaves Limited
Ankur Mangilal Borana
Executive Director and Chief Executive Officer
(DIN: 01091164)
Encl: Clean Max Letter