EXTENSION OF COMPLETION SCHEDULE OF GURDASPUR-JAMMU PIPELINE (GJPL) PROJECT
Gail (India) Ltd · 532155
✦ AI SummaryExpansion
Gail (India) Ltd has extended the completion schedule of its Gurdaspur-Jammu Pipeline (GJPL) project to December 2026 due to delay in receipt of forest permission in Punjab. The project's revised length is 153 km, with 78 km already commissioned. No additional investment is required.
Analysis Scores
Earnings Impact2/10
Growth Catalyst4/10
Governance Concern1/10
Regulatory Risk3/10
Balance Sheet Risk1/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Gail (India) Ltd - 532155 - Disclosure Of Event Or Information Under Regulation 30 Of SEBI LODR Regulations, 2015
Attachments (1)
📄pdf
Download →
5e56d0c0-6f12-4970-b38e-13b52b29b2c0.pdf
View document text
ND/GAIL/SECTT/2026 30.10.2026
Listing Compliance Listing Compliance
National Stock Exchange of India Limited BSE Limited
Exchange Plaza, 5th Floor, Plot No. C/1 Floor 1, Phiroze Jeejeebhoy
G Block, Bandra-Kurla Complex Towers, Dalal Street
Bandra (East) Mumbai – 400051 Mumbai – 400001
Scrip Code: GAIL-EQ Scrip Code: 532155
Sub: Disclosure of event or information under Regulation 30 of SEBI LODR
Regulations, 2015
Sir/Madam,
This is in continuation of our letter dated 26.08.2023.
Please find below disclosure pertaining to event or information as stipulated in Regulation 30 of
SEBI (LODR) Regulations, 2015:
EXTENSION OF COMPLETION SCHEDULE OF GURDASPUR-JAMMU PIPELINE
(GJPL) PROJECT
a Pipeline GURDASPUR-JAMMU PIPELINE (GJPL) PROJECT
b Length Authorized/ under 160 Km / 153 Km
execution (Revised Length)
c Pipeline Completed 153 Km
d Pipeline Commissioned 78 Km
e Revised Completion December, 2026
Schedule
f Additional Investment Not required
required
g Rationale Delay in receipt of forest permission in Punjab Section of
GJPL
Further, approval for extension in completion schedule of aforesaid project(s) is being taken up
with PNGRB.
It was approved by the Board of Directors of the Company in its meeting held today i.e.
30.10.2026 which commenced at 11.00 a.m. and concluded at 02:25 p.m.
This disclosure is in compliance of SEBI (Listing Obligations and Disclosure Requirements)
Regulations, 2015.
Thanking you
Yours faithfully
(Deepak Asija)
Company Secretary
Copy to:
1. Deutsche Bank AG, Filiale Mumbai
TSS & Global Equity Services
The Capital, 14th Floor
C-70, G Block, Bandra Kurla Complex
Mumbai -400051
2. Beacon Trusteeship Limited
4C and D Siddhivinayak Chambers,
Gandhi Nagar, Opposite MIG Cricket club,
Bandra East, Mumbai -400051