BSECompany Update1d ago · 30 Oct 2026, 02:48 pm
EXTENSION OF COMPLETION SCHEDULE OF KOCHI- KOOTTANADBENGALURU- MANGALURU PIPELINE (KKBMPL) PROJECT
Gail (India) Ltd · 532155
✦ AI SummaryOrder Win
Gail (India) Ltd has extended the completion schedule of the Kochi-Koottanad-Bengaluru-Mangaluru Pipeline (KKBMPL) project to March 2027 due to delay in availability of hindrance-free fronts.
Analysis Scores
Earnings Impact2/10
Growth Catalyst3/10
Governance Concern1/10
Regulatory Risk2/10
Balance Sheet Risk1/10
Liquidity Impact5/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Gail (India) Ltd - 532155 - Disclosure Of Event Or Information Under Regulation 30 Of SEBI LODR Regulations, 2015
Attachments (1)
📄pdf
Download →
3f040717-61b4-4bae-9522-7b920c1019c5.pdf
View document text
ND/GAIL/SECTT/2026 30.10.2026
Listing Compliance Listing Compliance
National Stock Exchange of India Limited BSE Limited
Exchange Plaza, 5th Floor, Plot No. C/1 Floor 1, Phiroze Jeejeebhoy
G Block, Bandra-Kurla Complex Towers, Dalal Street
Bandra (East) Mumbai – 400051 Mumbai – 400001
Scrip Code: GAIL-EQ Scrip Code: 532155
Sub: Disclosure of event or information under Regulation 30 of SEBI LODR
Regulations, 2015
Sir/Madam,
This is in continuation of our letter dated 13.04.2026.
Please find below disclosure pertaining to event or information as stipulated in Regulation 30 of
SEBI (LODR) Regulations, 2015:
EXTENSION OF COMPLETION SCHEDULE OF KOCHI- KOOTTANAD-
BENGALURU- MANGALURU PIPELINE (KKBMPL) PROJECT
a Pipeline KOCHI- KOOTTANAD- BENGALURU-
MANGALURU PIPELINE (KKBMPL) PROJECT
b Length Authorized/ under 1104 Km / 951 Km
execution (Revised Length)
c Pipeline Completed 947 Km
d Pipeline Commissioned 715 Km
e Revised Completion Schedule March, 2027
f Additional Investment required Not Required
g Rationale Delay in availability of hindrance free fronts
Further, approval for extension in completion schedule of aforesaid project(s) is being taken up
with PNGRB.
It was approved by the Board of Directors of the Company in its meeting held today i.e.
30.10.2026 which commenced at 11.00 a.m. and concluded at 02:25 p.m.
This disclosure is in compliance of SEBI (Listing Obligations and Disclosure Requirements)
Regulations, 2015.
Thanking you
Yours faithfully
(Deepak Asija)
Company Secretary
Copy to:
1. Deutsche Bank AG, Filiale Mumbai
TSS & Global Equity Services
The Capital, 14th Floor
C-70, G Block, Bandra Kurla Complex
Mumbai -400051
2. Beacon Trusteeship Limited
4C and D Siddhivinayak Chambers,
Gandhi Nagar, Opposite MIG Cricket club,
Bandra East, Mumbai -400051