NSECapacity addition26 Oct 2026 · 26 Oct 2026, 02:37 pm
Capacity addition
Ather Energy Limited · ATHERENERG
✦ AI Summary▲ PositiveExpansion
Ather Energy Limited has informed the Exchange that the Board has approved proposals for the enhancement of manufacturing capacity at its factories in Hosur, Tamil Nadu and Chhatrapati Sambhajinagar, Maharashtra. The proposed expansion will increase the annual production capacity of electric two-wheelers at the Hosur factory and the planned annual production capacity of Factory 3.0.
Analysis Scores
Earnings Impact8/10
Growth Catalyst9/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact9/10
Market Sentiment8/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Ather Energy Limited has informed the Exchange that the Board at the meeting held today has considered and approved proposals for the enhancement of manufacturing capacity at the Companys factories located at Hosur, Tamil Nadu and Chhatrapati Sambhajinagar, Maharashtra (Factory 3.0- under construction).
Attachments (1)
📄pdf
Download →
ATHERENERGY_26102026143153_CapacityAdditionsigned.pdf
View document text
October 26, 2026
To To
National Stock Exchange of India Ltd BSE Limited
Exchange Plaza, 5th Floor, C-1, Block G, 1st Floor, Phiroze Jeejeebhoy Towers
Bandra Kurla Complex, Bandra (E), Mumbai 400051 Dalal Street Mumbai – 400001
NSE Symbol: ATHERENERG Scrip Code: 544397
Subject: Disclosure under Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations,
2015
Dear Sir/ Madam,
Pursuant to Regulation 30 of the Securities and Exchange Board of India (Listing Obligations and Disclosure
Requirements) Regulations, 2015 (‘SEBI Listing Regulations’), we wish to inform you that the Board at the meeting
held today, i.e., October 26, 2026, has considered and approved proposals for the enhancement of manufacturing
capacity at the Company’s factories located at Hosur, Tamil Nadu and Chhatrapati Sambhajinagar, Maharashtra
(Factory 3.0- under construction). Capital Expenditure (CAPEX) of approximately INR 122 Crores (including taxes)
has been earmarked for the said expansion.
The proposed expansion will increase the annual production capacity of electric two-wheelers at the Hosur factory
from 420,000 units to 495,000 units, and the planned annual production capacity of Factory 3.0 from 500,000
units to 650,000 units.
The disclosures required under Regulation 30 of SEBI Listing Regulations, read with Part A of Schedule III of the
SEBI Listing Regulations and relevant SEBI Circulars are provided in Annexure A.
The meeting of the Board of Directors of the Company commenced at 09:10 AM (IST) and concluded at 02:15 PM
(IST).
Kindly take the above information on record.
Thank you
For Ather Energy Limited
Puja Aggarwal
Company Secretary & Compliance Officer
Membership No: A49310
Annexure-A
S. No. Particulars Hosur Factory Factory 3.0 at Chhatrapati
Sambhajinagar
1 Existing capacity 420,000 units per annum 500,000 units per annum (under
construction)
2 Existing capacity utilization 98% at peak production Plant under construction
3 Proposed capacity addition 75,000 units per annum 150,000 units per annum
4 Period within which the Capacity addition is expected Capacity addition is expected to
proposed capacity is to be to be completed in December, be completed in Q2 FY28
added 2026
5 Investment required Upto INR 58 crore (incl tax)* Upto INR 64 crore (incl tax)
6 Mode of financing Combination of debt and Combination of debt and internal
internal accruals accruals
7 Rationale Scale up long-term Scale up long-term
manufacturing output to meet manufacturing output to meet
the business demand the business demand
*Includes an investment of INR 53 crores in a new battery line to cater to demand scenarios and to de-risk
supply chain. This is expected to be completed by Q3 FY28.