BSECompany Update23 Oct 2026 · 23 Oct 2026, 05:01 pm
Commissioning of project namely "Transmission scheme for integration of Renewable Energy Zone (Phase-II) in Koppal-II (Phase-A & B) and Gadag-II (Phase-A) in Karnataka.
Power Grid Corporation of India Ltd · 532898
✦ AI SummaryOrder Win
Power Grid Corporation of India Ltd has commissioned the 'Transmission Scheme for integration of Renewable Energy Zone (Phase-II) in Koppal-II (Phase-A & B) and Gadag-II (Phase- A) in Karnataka' project, effective from 23rd October, 2026.
Analysis Scores
Earnings Impact2/10
Growth Catalyst6/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk1/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Power Grid Corporation of India Ltd - 532898 - Commissioning Of Project Namely 'Transmission Scheme For Integration Of Renewable Energy Zone (Phase-II) In Koppal-II (Phase-A & B) And Gadag-II (Phase- A) In Karnataka'.
Attachments (1)
📄pdf
Download →
70386697-ce01-4168-b286-1683391bbe63.pdf
View document text
23rd October, 2026
To To
The General Manager (Listing), The General Manager (Listing),
National Stock Exchange of India Limited, BSE Limited,
Exchange Plaza, C 1/G Block, Phiroze Jeejeebhoy Towers,
Bandra-Kurla Complex, Dalal Street, Mumbai.
Bandra (East), Mumbai.
Reference: NSE-SCRIP ID: POWERGRID; BSE Scrip Code: 532898
EQ – ISIN INE752E01010
Sub.: Commissioning of project namely “Transmission Scheme for integration
of Renewable Energy Zone (Phase-II) in Koppal-II (Phase-A & B) and
Gadag-II (Phase- A) in Karnataka”.
Dear Sir,
In terms of Regulation 30 of the SEBI (Listing Obligations and Disclosure
Requirements) Regulations, 2015, as amended, this is to inform that the project namely
“Transmission Scheme for integration of Renewable Energy Zone (Phase-II) in
Koppal-II (Phase-A & B) and Gadag-II (Phase- A) in Karnataka” (‘Project’) has been
completely commissioned with effect from 23rd October, 2026 for which Notification for
Commercial Operation (DOCO) has been received on 23rd October, 2026. The Project was
entrusted to POWERGRID Koppal Gadag Transmission Ltd (PKGTL), then a wholly owned
subsidiary of Power Grid Corporation of India Ltd., which is amalgamated with
POWERGRID Khavda II-C Transmission Limited w.e.f. 01st March 2026 as per order dated
27th January, 2026 of the Ministry of Corporate Affairs (MCA).
This is for your information and record please.
Thanking You,
Yours faithfully,
(Anjana Luthra)
Company Secretary &
Compliance Officer
Corporate Office: “Saudamini”, Plot No. 2, Sector-29, Gurugram-122001, (Haryana) Tel.: 0124-2822999 & 2822000
Registered Office: B-9, Qutab Institutional Area, Katwaria Sarai, New Delhi-110 016. Tel: 011-26560112, 26560115 & 26560193,
CIN : L40101DL1989GOI0381 21
Website: www.powergrid.in