Pitti Engineering Ltd has approved a capex of ₹450 crores to increase manufacturing capacities and value-addition capabilities, with the project to be implemented in phases up to FY 2030-31.
Analysis Scores
Earnings Impact8/10
Growth Catalyst9/10
Governance Concern1/10
Regulatory Risk2/10
Balance Sheet Risk3/10
Liquidity Impact9/10
Market Sentiment8/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Pitti Engineering Ltd-$ - 513519 - Announcement Under Regulation 30 Of SEBI (LODR)
Attachments (1)
📄pdf
Download →
54c9f01d-ea14-40e9-bd22-1866837d4024.pdf
View document text
22nd October 2026
To, To,
BSE Limited National Stock Exchange of India Limited
Floor 25, P J Towers, Dalal Street Exchange Plaza, Bandra Kurla Complex
Mumbai – 400 001 Bandra (E), Mumbai – 400 051
Scrip Code: 513519 Scrip Code: PITTIENG
Dear Sirs,
Sub: Approval of Capex and capacity expansion
We wish to inform you that the Board of Directors of the Company at its meeting held today i.e. 22nd October 2026 has
approved a capex of ₹450 crores to increase manufacturing capacities and value-addition capabilities and consolidate the
Company's fragmented lamination manufacturing operations in Karnataka into a single integrated manufacturing facility.
The project is proposed to be implemented in phases up to FY 2030-31.
The relevant details as required under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements)
Regulations, 2015 read with SEBI Master Circular No. HO/49/14/14(7)2025-CFD-POD2/I/3762/2026 as updated on
30th January 2026 is attached as Annexure.
Kindly take the same on record.
Thanking you,
Yours faithfully,
For Pitti Engineering Limited
Mary Monica Braganza
Company Secretary & Chief Compliance Officer
FCS: 5532
Annexure
Disclosure under Regulation 30 of SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015 and
SEBI Master Circular No. HO/49/14/14(7)2025-CFD-POD2/I/3762/2026 as updated on 30th January 2026.
Approved capital expenditure and capacity expansion
Sno Particulars Details
a) Existing capacity The current consolidated installed capacity for sheet metal (lamination) is
1,08,000 MT per annum and for machining hours is 8,13,600 with an
approved expansion currently underway to enhance machining capacity
to 10,80,000 machining hours by Q1 2029-30.
b) Existing capacity utilization The current capacity utilisation stands at ~ 78% for sheet metal and ~ 85%
for machining.
c) Proposed capacity addition
Particulars Existing On-going Post
(Per annum) Capacity as Capacity Proposed
on addition to be Capacity
30-Sep-2026 completed by
Q1 2029-30
Sheet Metal (MT) 1,08,000 NA 1,60,000
Machine Hours 8,13,600 10,80,000 13,14,000
d) Period within which the proposed The project is proposed to be implemented in phases up to FY 2030-31.
capacity is to be added
e) Investment required Estimated project cost is ₹ 450 crores
f) Mode of financing Internal accruals and Debt
g) Rationale The Company is witnessing sustained growth in demand across key
sectors, including mining and off-highway vehicles, power generation
(including thermal, hydro, pumped storage and wind energy), data
centres, railways and metro infrastructure. In order to support the
anticipated growth in business volumes, strengthen its manufacturing
capabilities and enhance value addition, the Company proposes to
undertake capacity expansion and consolidate its presently fragmented
lamination manufacturing operations in Karnataka into a single integrated
manufacturing facility. The project is expected to increase capacities,
improve operational efficiencies, optimise costs and support future
growth.