BSECompany Update8 Oct 2026 · 8 Oct 2026, 01:10 pm
Intimation
Kabra Extrusiontechnik Ltd · 524109
✦ AI Summary▲ PositiveOrder Win
Kabra Extrusiontechnik Ltd has successfully executed and commissioned a 10 MW / 20 MWh Battery Energy Storage System (BESS) project at Jaisalmer, Rajasthan, on EPC basis.
Analysis Scores
Earnings Impact2/10
Growth Catalyst6/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk1/10
Liquidity Impact8/10
Market Sentiment7/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Kabra Extrusiontechnik Ltd - 524109 - Intimation Under Regulation 30 Of The SEBI (Listing Obligations And Disclosure Requirements) Regulations, 2015 - Successful Execution And Commissioning Of 10 MW / 20 Mwh BESS Project
Attachments (1)
📄pdf
Download →
b3519844-f71d-4186-a3df-011259e03444.pdf
View document text
KET/SEC/SE/2026-27/49 October 08, 2026
BSE Limited National Stock Exchange India Ltd.
Floor 25, Phiroze Jeejeebhoy Tower, Exchange Plaza, C-1, Block-G,
Dalal Street, Bandra Kurla Complex, Bandra (East),
Mumbai – 400 001 Mumbai-400051
Scrip Code: 524109 S t o c k C o d e : K A B R A E X T R U
Sub: Intimation under Regulation 30 of the SEBI (Listing Obligations and Disclosure
Requirements) Regulations, 2015 – Successful Execution and Commissioning of 10 MW /
20 MWh BESS Project
Dear Sir/Madam,
The Company is pleased to inform that GEON, its New Energy business division, has successfully
executed and commissioned a 10 MW / 20 MWh Battery Energy Storage System (BESS) Project
at Jaisalmer, Rajasthan, on EPC basis.
The project scope encompassed detailed engineering and design, procurement and supply of
equipment, installation, testing and commissioning activities, in accordance with the Rajasthan
Integrated Clean Energy Policy, 2024.
The Battery Energy Storage System has been designed to support efficient energy management,
grid stability and effective integration of renewable energy, thereby contributing towards a
more reliable and sustainable energy infrastructure.
The successful commissioning of this project marks a significant milestone for the Company and
reinforces GEON's capabilities in delivering utility-scale Battery Energy Storage System (BESS)
projects on a turnkey EPC basis. The project further strengthens the Company's position in the
energy storage and renewable energy sector and underscores its commitment to supporting
India's clean energy transition and grid modernization initiatives.
You are requested to take the above information on record.
Thanking you,
Yours faithfully,
For Kabra Extrusiontechnik Limited
Hiren Vala
Company Secretary & Compliance Officer
www.kolsite.com A Kolsite Group
Company
Kabra Extrusiontechnik Limited
Fortune Terraces, B wing, 10th Floor, Link Road, Opp. Citi Mall,
Andheri (West), Mumbai - 400 053. Maharashtra, India.
Phone : +91-022-6735 3333 Email : sales@kolsitegroup.com
CIN - L28900MH1982PLC028535