View document text
Date: June 22, 2026
Department of Corporate Services
BSE Limited
P. J. Towers, Dalal Street,
Fort, Mumbai – 400001
Company Scrip ID: GHVINFRA
Company Scrip Code: 505504
Sub: Intimation under Regulation 30 of the SEBI (Listing Obligations and Disclosures
Requirements) Regulations, 2015 – Receipt of Work Order (WO)
Dear Sir/Madam,
With reference to the captioned subject, we wish to inform you that GHV Infra Projects
Limited (‘the Company’) has received the Work Order from GHV (India) Private Limited for
the Composite work (Civil, Electrical, Mechanical and Signal & Telecom) involving
construction (A) Upgradation / Development of maintenance infrastructure at Coaching
Complex. (B) Next Generation Freight Maintenance Facilities (C) Infrastructure construction
of Loco shed in West Bengal.
The order is valued at approximately Rs. 213 Crore (Rupees Two Hundred and Thirteen
Crore) including GST and it is required to be completed within period of 14 (fourteen) months
from the date of commencement.
The details required as per SEBI Master Circular HO/49/14/14(7)2025-CFD-
POD2/I/3762/2026 dated January 30, 2026 are given in the Annexure - I
You are requested to kindly take the same on record.
Thanking you,
Yours faithfully
For GHV Infra Projects Limited
(Formerly known as Sindu Valley Technologies Limited)
Daksh Tulsibhai Mewada
Company Secretary & Compliance Officer
Registered Office: A-511, 5th Floor, Kanakia Wall Street, Andheri Kurla Road, Andheri (East), Chakala MIDC,
Mumbai – 400093.Tel: +91 22 6941 1500, Email: info@ghvinfra.com Web: www.ghvinfra.com
CIN No.: L43900MH1976PLC457495
Annexure - I
Particulars Details
Name of the entity awarding the order(s)/ GHV (India) Private Limited
contract(s); (CIN: U45202MH2009PTC196564)
Significant terms and conditions of For the Composite work (Civil, Electrical,
order(s)/ contract(s) awarded in brief Mechanical and Signal & Telecom) involving
construction (A) Upgradation /
Development of maintenance infrastructure
at Coaching Complex. (B) Next Generation
Freight Maintenance Facilities (C)
Infrastructure construction of Loco shed in
West Bengal.
The Work Order is valued at approximately
Rs. 213 Crore (Rupees Two Hundred and
Thirteen Crore) including GST and it is
required to be completed within period of 14
(fourteen) months from the date of
commencement.
Whether order(s)/contract(s) have been Domestic
awarded by domestic/ international entity;
Nature of order(s)/contract(s) Work Order
Time period if any, associated with the To be completed within 14 (fourteen) months
order(s)/contract(s) from the date of commencement
Broad commercial consideration or size of The Work Order is valued at approximately
the order(s)/contract(s) Rs. 213 crore (Rupees Two Hundred and
Thirteen Crore) Including GST.
Whether the promoter/ promoter group / Yes. Mr. Jahidmohmed Vijapura is deemed
group companies have any interest in the promoter of the GHV Infra Projects Limited.
entity that awarded the Mr. Jahidmohmed Vijapura who is
order(s)/contract(s)? If yes, nature of Designated partner/Partner in JHV
interest and details thereof; Commercials LLP and said LLP is holding
major stake in the GHV Infra Projects
Limited.
Mr. Jahidmohmed Vijapura is also Director
and shareholder of GHV (India) Private
Limited.
Whether the order(s)/contract(s) would fall Yes, and it is done at arm’s Length basis.
within related party transactions? If yes,
whether the same is done at “arm’s length
Registered Office: A-511, 5th Floor, Kanakia Wall Street, Andheri Kurla Road, Andheri (East), Chakala MIDC,
Mumbai – 400093.Tel: +91 22 6941 1500, Email: info@ghvinfra.com Web: www.ghvinfra.com
CIN No.: L43900MH1976PLC457495