SEPC Limited has announced that the Madras High Court has lifted the attachment on its ₹154 crore receivables following a dispute settlement, with no direct monetary outflow for the company.
Analysis Scores
Earnings Impact8/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk1/10
Liquidity Impact9/10
Market Sentiment8/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
We hereby informed the Exchange of the press release titled "Major Relief for SEPC as Madras High Court Lifts Attachment on Rs.154 Crore Receivables Following Dispute Settlement". Detailed letter is enclosed.
Attachments (1)
📄pdf
Download →
SHRIRAMEPC_05102026084430_SE_INTIMATION_WITH_PRESS_RELEASEsd.pdf
View document text
October 5, 2026
National Stock Exchange of India Limited BSE Limited
Exchange Plaza, 5th Floor, 14th Floor, PJ Towers,
Bandra Kurla Complex, Dalal Street,
Mumbai 400051 Mumbai 400001
NSE SYMBOL: SEPC Scrip Code: 532945
Dear Sir/Madam,
Sub: Press release titled “Major Relief for SEPC as Madras High Court Lifts Attachment
on ₹154 Crore Receivables Following Dispute Settlement”
Ref: Regulation 30 of the Securities and Exchange Board of India (Listing Obligations and
Disclosure Requirements) Regulations, 2015
Dear Sir/Madam,
Pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements)
Regulations, 2015, we hereby enclose the following document:
A Press Release titled “Major Relief for SEPC as Madras High Court Lifts Attachment
on ₹154 Crore Receivables Following Dispute Settlement”.
The Press Release highlights the attachment on the Company's receivables of ₹154 crore has
been removed with immediate effect, and all restrictions on its banking operations have been
completely lifted. Importantly, the settlement involves no direct monetary outflow for SEPC, as
the entire settlement amount has been paid by another party to the proceedings under a 2015
indemnity agreement.
The said press release will be simultaneously posted on the Company’s website
https://www.sepc.in/.
You are requested to kindly take the same on record.
Thanking you,
Yours faithfully,
For SEPC Limited
T Sriraman
Company Secretary & Compliance Officer
Encl.: a.a
Major Relief for SEPC as Madras High Court Lifts Attachment on ₹154 Crore
Receivables Following Dispute Settlement
Chennai, October 5, 2026: SEPC Limited (NSE: SEPC | BSE: 532945), a leading EPC company with established
expertise in industrial infrastructure, process plants, water and wastewater management, has announced that the Hon'ble
High Court of Madras, through its Common Order dated September 30, 2026, has brought a full and final closure to the
execution proceedings filed against the Company and other co-parties by the Award Holders. The Court has terminated
all the related Execution Petitions and closed all connected pending applications, following a Joint Memo of Compromise
executed between the parties.
The order marks a significant positive development for SEPC. The attachment on the Company's receivables of ₹154
crore has been removed with immediate effect, and all restrictions on its banking operations have been completely lifted.
Importantly, the settlement involves no direct monetary outflow for SEPC, as the entire settlement amount has been paid
by another party to the proceedings under a 2015 indemnity agreement.
Key Highlights of the Order
Full and final settlement: The parties agreed to a total settlement of ₹149.5 crore, comprising a Demand Draft of
₹147 crore submitted before the Court and ₹2.5 crore already lying to the credit of the Court, which will be paid to
the Award Holders.
Nil outflow for SEPC: The settlement amount has been paid entirely by another party under a 2015 indemnity
agreement, with no direct monetary outflow for the Company.
₹154 crore of receivables unlocked: All interim attachments made under these petitions now stand raised, releasing
receivables of ₹154 crore with immediate effect.
Banking operations restored: All restrictions on the Company's banking operations have been completely lifted
with immediate effect.
All proceedings closed: All listed and un-numbered Execution Petitions have been terminated and all connected
pending applications closed.
With this order, all long-standing disputes and the related execution liabilities under these petitions stand fully concluded
and settled.
Commenting on the development, Mr. Venkataramani Jaiganesh, Managing Director, SEPC Limited, said:
“We welcome the order of the Hon'ble High Court of Madras, which brings these long-standing proceedings to a full
and final closure. The matter has been settled with no direct cash outflow for SEPC, and the release of ₹154 crore of
receivables, along with the lifting of all banking restrictions, gives the Company greater financial flexibility with
immediate effect. With this matter now behind us, our focus remains firmly on project execution and on delivering
sustainable growth for all our stakeholders.”
About SEPC Limited
SEPC Limited (formerly Shriram EPC Limited) is a well-established EPC company offering turnkey solutions across
Water & Wastewater, Roads, Industrial Infrastructure, and Mining sectors. The company specializes in the design,
procurement, construction, and commissioning of large and complex infrastructure projects across India.
SEPC serves a wide range of clients, including Central and State Government agencies, and continues to play a key role
in India's infrastructure development.
In FY26, the Company delivered Total Income of ₹1,085.8 Cr, EBITDA of ₹108.9 Cr, and Net Profit of ₹53.5 Cr,
against Total Income of ₹646.0 Cr in FY25, with Net Profit more than doubling over the previous year.
Disclaimer
Certain statements in this document that are not historical facts are forward looking statements. Such forward-looking
statements are subject to certain risks and uncertainties like government actions, local, political or economic
developments, technological risks, and many other factors that could cause actual results to differ materially from
those contemplated by the relevant forward-looking statements. The Company will not be in any way responsible for
any action taken based on such statements and undertakes no obligation to publicly update these forward-looking
statements to reflect subsequent events or circumstances.