Vikran Engineering Limited has informed the Exchange regarding the cancellation of an order received from Ellume Energy MH Solar One Private Limited due to prolonged delays in achieving project readiness milestones.
Analysis Scores
Earnings Impact6/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk1/10
Liquidity Impact8/10
Market Sentiment4/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Vikran Engineering Limited has informed the Exchange regarding cancellation of Order received from Ellume Energy MH Solar One Private Limited
Attachments (1)
📄pdf
Download →
VIKRAN123_27062026142619_Intimation_of_Cancellation_of_Award-Ellume.pdf
View document text
Date: 27th June 2026
To, To,
The Secretary The Secretary
BSE Limited National Stock Exchange of India Limited
Corporate Relationship Department, Listing Department,
Phiroze Jeejeebhoy Towers, Dalal Street, Exchange Plaza, Bandra-Kurla Complex, Bandra
Mumbai-400001. (E), Mumbai –400051.
(Scrip Code: Equity - 544496) (Scrip Symbol: VIKRAN)
Dear Sir/Madam,
Sub.: Disclosure of information under Regulation 30 of the SEBI (Listing Obligations and Disclosure
Requirements) Regulations, 2015 (“SEBI Listing Regulations”)
Pursuant to Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015 and
further to the Company’s earlier intimation dated 24th October 2025 regarding acceptance of Letter of Award
from Ellume Energy MH Solar One Private Limited (SPV) aggregating to approximately ₹354.21 crore, Vikran
Engineering Limited (“the Company”) hereby informs that, based on a detailed internal evaluation, the
Company has decided not to proceed with the said order.
The cancellation is primarily on account of prolonged delays in achieving the necessary project readiness
milestones at the client's end. The client was unable to provide the required Power Purchase Agreement (PPA),
work commencement approvals, design clearances, scope finalization, and mobilization permissions within the
expected timelines. Consequently, the commencement of the project remained uncertain, making execution of
the work order commercially unviable.
The cancellation of the aforesaid work order is by mutual understanding between the parties and is not
expected to have any material adverse impact on the overall business operations or financial performance of
the Company. The Company continues to remain focused on opportunities that are strategically aligned,
execution-ready, and accretive to long-term shareholder value.
Further, the disclosure as required under Schedule III of the SEBI LODR Regulations read with SEBI Circular
No. SEBI/HO/49/14/14(7)2025-CFD-POD2/I/3762/2026 dated January 30, 2026, as amended read with
Regulation 30 of the SEBI (LODR) Regulations is attached herewith and marked as Annexure I to this letter.
This is for your information and records.
Thanking You.
Yours faithfully,
FOR VIKRAN ENGINEERING LIMITED
Kajal Rakholiya
Company Secretary and Compliance Officer
Place: Thane
Encl.: as above
ANNEXURE -I
Details under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements)
Regulations, 2015 read along with SEBI Circular No. SEBI/HO/49/14/14(7)2025-CFD-POD2/I/3762/2026
dated January 30, 2026
Sr. No. Particulars Details
1 name of parties to the Ellume Energy MH Solar One Private Limited (SPV)
order(s)/contract(s);
2 nature of order(s) / contract(s); Turnkey Engineering, Procurement, and Construction
(EPC) Contract for the 100 MW AC Solar Power
Project in Maharashtra
3 date of execution of the LOA accepted on dated 24th October 2025
order(s)/contract(s)
4 details of amendment or reasons for The cancellation is primarily on account of prolonged
terminations and impact thereof (to the delays in achieving the necessary project readiness
extent possible); milestones at the client's end. The client was unable to
provide the required Power Purchase Agreement
(PPA), work commencement approvals, design
clearances, scope finalization, and mobilization
permissions within the expected timelines.
Consequently, the commencement of the project
remained uncertain, making execution of the work
order commercially unviable.
This development is not expected to have any
material adverse impact on the Company’s ongoing
operations, financial position, or growth outlook.