Intimation of Amendment in Work order
Nila Infrastructures Ltd · 530377
✦ AI SummaryOrder Win
Nila Infrastructures Ltd has received an amendment in the work order from Ahmedabad Municipal Corporation for the Slum Rehabilitation Work of 'Kajimiya ni Chali' at Ahmedabad, resulting in a reduction in the balance free sale land and an increase in the Transferable Development Rights (TDR).
Analysis Scores
Earnings Impact6/10
Growth Catalyst4/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Nila Infrastructures Ltd - 530377 - Announcement under Regulation 30 (LODR)-Award_of_Order_Receipt_of_Order
Attachments (1)
📄pdf
Download →
1d295ee0-659c-449e-b61c-9d57d8072eb0.pdf
View document text
NILA
INFRASTRUCTURES
Nila/Cs/2026/64
LIMITED
Date: 01 October 2026
To, To,
The General Manager The Manager
Department ofCorporate Services Listing Department
Bombay Stock Exchange Ltd. The National Stock Exchange of India Limited
P. J. Towers, Dalal Street Bandra - Kurla Complex
Mumbai -400 001 Mumbai -400 051
Scrip ID 530377 Scrip ID: NILAINFRA
DearSir,
Sub: Intimation ofAmendment ofWork Order, received from Ahmedabad Municipal
Corporation ("AMC"), forSlum Rehabilitation Work of"Kajimiya ni Chali" at
Ahmedabad
Ref: Regulation 30 ofSEBI (Listing Obligations and Disclosure Requirements)
Regulations 2015 read with SEBI Circular No CIRICFDICMD/4/2015 dated 09.09.2015
It is hereby submitted that the Company has on 01-10-2026, received intimation from AMC
for amendment of Slum Rehabilitation Project of "Kajimiya ni Chali" at Ahmedabad. In this
connection, the prescribed disclosure under the above referred regulation is enclosed
herewith as anAnnexure.
The intimation of amendment is received, underordinary course of business ofthe Company
as a regular business activity in normal course.
Kindly find the attachment herewith and take the same on your record.
Thanking you,
Yours faithfully,
For Nila Infrastructures Limited
Dipen Y. Parikh
Company Secretary
Encl: a/a
ReglsieredOffice:
1stfloor,SombhoovHouse
Opp.ChiefJustice'sBungalow
Bodokdev,Ahmedabad380015
Tel.: +91 7940036817/18,26870258
Fox:+91 7930126371
e-mail:info@niloinfro.com
CIN: L4520lGJ1990PLC013417
-4 1
ANNEXURE
Particulars Details
Name of the Party to the Work Ahmedabad Municipal Corporation ("AMC"]
Order.
Nature ofWorkOrder Originallythe project was awarded to the Company for development
of a slum "Kajimiya ni Chali" at Ahmedabad by constructing 728
housingunits and 25 commercial shops. The projectwas awarded by
AMC under the Slum Rehabilitation and Redevelopment Policy 2013
pursuant to Pradhanmantri Awas Yojna under PPP basis. Total
development cost ofthe project was INR 105.02 Crore for which the
Companywouldbe receivingTransferable Development Rights (TDR)
of INR 56.51 Crore and balance free sale land admeasuring 4209.61
sq.mfrs amountingto INR48.51 Crore.
Date ofExecutionof WorkOrder The work was originally awarded by AMC to the Company vide LOA
dated 04.10.2025 (received on 07.10.2025) and the present
intimationofamendmentisreceivedtodayon 01.10.2026.
Details of Amendment / The work is amended bythe AMC whereby the Company would now
Cancellation and its Effect be receiving reduced balance free sale land admeasuring 2290 sq.
thereon mfrs. of INR 26.39 Crore instead of 4209.61 sq. mfrs. of INR 48.51
Crore, in lieu of additional TDR of INR 22.12 Crore. Therefore, the
value of total TDR is increased to INR 78.63 Crore to compensate
reduction of size andvalue of land.