NSECommencement of commercial production/operations4d ago · 29 Sept 2026, 10:29 pm
Commencement of commercial production/operations
Juniper Green Energy Limited · JNPR
✦ AI Summary▲ PositiveExpansion
Juniper Green Energy Limited has informed the Exchange about commissioning of additional 100.64 MWh of Battery Energy Storage System (BESS) capacity under Bikaner Phase II, increasing the aggregate commissioned BESS capacity to 201.28 MWh.
Analysis Scores
Earnings Impact6/10
Growth Catalyst8/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact9/10
Market Sentiment8/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Juniper Green Energy Limited has informed the Exchange about commissioning of additional BESS capacity
Attachments (1)
📄pdf
Download →
JGEL2025_29092026222915_2026_09_29_JGEL_Reg_30_Letter_BESS_Commissioning-_Cosmic.pdf
View document text
Date: September 29, 2026
To, To,
National Stock Exchange of India Limited BSE Limited
Exchange Plaza, C-1 Block G, Phiroze Jeejeebhoy Towers,
Bandra-Kurla Complex Bandra (East), Dalal Street,
Mumbai – 400 051 Mumbai - 400 001
Symbol: JNPR Scrip Code: 544853
Sub: Intimation under Regulation 30 of the Securities and Exchange Board of India (Listing
Obligations and Disclosure Requirements) Regulations, 2015 – Update on commissioning of
additional BESS capacity
Dear Sir/ Madam,
This is to inform you that Juniper Green Cosmic Private Limited, a subsidiary of Juniper Green Energy
Limited, has commissioned 100.64 MWh of Battery Energy Storage System (BESS) capacity under
Bikaner Phase II at the project site today, i.e., September 29, 2026. With this commissioning, the
aggregate commissioned BESS capacity of Juniper Green Cosmic Private Limited has increased from
100.64 MWh to 201.28 MWh.
Pursuant to the commissioning of the above capacity, the aggregate operational capacity of Juniper
Green Energy Limited and its subsidiaries stands at ~2,725 MWp and ~600 MWh BESS as of the date
hereof.
We request you to kindly take the same on record.
Thanking You,
For Juniper Green Energy Limited
Prashant Pandia
Company Secretary and Compliance Officer
FCS 12077
Juniper Green Energy Limited
(Formerly known as Juniper Green Energy Private Limited)
Registered office: 1103A & 1103B, 11th Floor, Hemkunt Chamber, 89, Nehru Place, New Delhi- 110019
Corporate office: 3rd and 4th Floor, Building 4, Candor TechSpace, Sector 48, Gurugram – 122001, Haryana
CIN: L40100DL2011PLC228318 Email: cs@junipergreenenergy.com; website: www.junipergreenenergy.com/ Tel +91-124 4739600, Fax +91-124 4739666