✦ AI Summaryagreements
IRB Infrastructure Developers Limited has informed the Exchange about the execution of Project Implementation / Management Agreements with IRB InvIT Fund to act as the Project Manager for the projects operated by Solapur Yedeshi Tollway Limited and CG Tollway Limited.
Analysis Scores
Earnings Impact5/10
Growth Catalyst2/10
Governance Concern1/10
Regulatory Risk3/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
IRB Infrastructure Developers Limited has informed the Exchange about Execution of Project Implementation / Management Agreements with IRB InvIT Fund to act as the Project Manager
Attachments (1)
📄pdf
Download →
IRB_29092026105601_SE_Discl_PIA_Execution_IRBIDLsd.pdf
View document text
Date: September 29, 2026
Corporate Relationship Department, Listing Department,
BSE Limited National Stock Exchange of India Limited
Phiroze Jeejeebhoy Towers Exchange Plaza, C-1 Block G,
Dalal Street, Mumbai 400 001. Bandra Kurla Complex, Bandra (E), Mumbai 400 051
Dear Sir / Ma’am,
Ref: Scrip Code: 532947, Symbol: IRB
Sub: Execution of Project Implementation / Management Agreements with IRB InvIT Fund to act as
the Project Manager.
We refer to our earlier disclosures dated July 2, 2026, regarding the approval to enter into Project
Implementation / Management Agreements (“PIA”) with IRB InvIT Fund (“Public InvIT”) to act as the
Project Manager, in pursuance to the Securities and Exchange Board of India (Infrastructure Investment
Trusts) Regulations, 2014, as amended, in connection with the projects operated by Solapur Yedeshi
Tollway Limited (“SYTL”) and CG Tollway Limited (“CGTL”) (collectively referred as “Project SPVs”),
as the Project SPVs of the Public InvIT, post transfer of the Project SPVs from the IRB Infrastructure Trust
to the Public InvIT for the balance concession period.
Please note that the Company has now executed the Project Implementation / Management Agreements to
act as the Project Manager in respect of the projects operated by each of the Project SPVs, post completion
of the transfer of 100% of the equity share capital of each of the Project SPVs from the IRB Infrastructure
Trust to the Public InvIT.
The details of the aforesaid approval for execution of project implementation agreements to act as Project
Manager, as required in pursuance of SEBI Master circular no. HO/49/14/14(7)2025-CFD-
POD2/I/3762/2026 dated January 30, 2026, are annexed herewith as Annexure I.
You are requested to kindly take note of the same.
For IRB Infrastructure Developers Limited
Mehul Patel
Company Secretary
Encl. as above
Annexure I
Details of Project Implementation Agreement
a) name(s) of parties with whom the Project SPVs namely -
agreement is entered; 1. Solapur Yedeshi Tollway Limited (“SYTL”),
2. CG Tollway Limited (“CGTL”)
b) purpose of entering into the agreement; The Company entering into the project
implementation agreements for each of:
1. SYTL - Four Laning of Solapur to Yedeshi
section of NH-211 from km 0.000 to km
100.000 (Design Length 98.717 km) in the State
of Maharashtra under NHDP Phase IV on
Design, Build, Finance, Operate and Transfer
(DBFOT) Toll basis.
2. CGTL – Six Laning of Kishangarh Udaipur
Ahmedabad Section from km 90.000 (near
Gulabpura) to km 214.870 (end of Chittorgarh
Bypass) of NH-79 in the State of Rajasthan
Package-2 under NHDP Phase – V on BOT
(Toll) mode.
c) shareholding, if any, in the entity with None
whom the agreement is executed;
d) significant terms of the agreement (in Approximately, Rs.2,663 crore on fixed price basis
brief) special rights like right to appoint (inclusive of applicable taxes) over the balance
directors, first right to share subscription concession period, which is approximately 18 years
in case of issuance of shares, right to on weighted average life.
restrict any change in capital structure
etc.;
e) Whether the said parties are related to No, the said parties are not related to promoter /
promoter/promoter group/ group promoter group / group companies in any manner.
companies in any manner. If yes, nature
of relationship;
f) whether the transaction would fall It is not a related party transaction under the SEBI
within related party transactions? If yes, (Listing Obligations and Disclosure Requirements)
whether the same is done at “arm’s Regulations, 2015.
length”
g) in case of issuance of shares to the None
parties, details of issue price, class of
shares issued;
h) any other disclosures related to such Not Applicable
agreements, viz., details of nominee on
the board of directors of the listed entity,
potential conflict of interest arising out
of such agreements, etc.;
i) in case of termination or amendment of Not Applicable
agreement, listed entity shall disclose
additional details to the stock
exchange(s):
i. name of parties to the agreement;
ii. nature of the agreement;
iii. date of execution of the agreement;
iv. details of amendment and impact
thereof or reasons of termination and
impact thereof.