NSECommencement of commercial production/operations6d ago · 15 Jul 2026, 11:05 pm
Commencement of commercial production/operations
Acme Solar Holdings Limited · ACMESOLAR
✦ AI Summary▲ PositiveExpansion
Acme Solar Holdings Limited has commissioned a 110.336 MWh capacity of Battery Energy Storage System (BESS) Project, with a commercial operation date (COD) scheduled for July 17, 2026. This marks a significant milestone for the company, with its wholly owned subsidiary, ACME Suryodaya Private Limited, achieving a commissioned capacity of 285 MW / 952.960 MWh.
Analysis Scores
Earnings Impact8/10
Growth Catalyst9/10
Governance Concern1/10
Regulatory Risk2/10
Balance Sheet Risk5/10
Liquidity Impact9/10
Market Sentiment8/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Acme Solar Holdings Limited has informed the Exchange about commissioning of Battery Energy Storage System (BESS) Project
Attachments (1)
📄pdf
Download →
ACMECS_15072026230022_Suryodaya-110.pdf
View document text
Leading Through Innovation
July 15, 2026
To To
BSE Limited National Stock Exchange of India Ltd
Corporate Relationship Dept., Corporate Relationship Dept.,
Phiroze Jeejeebhoy Towers, Exchange Plaza, Plot No. C/1, G Block,
Dalal Street, Mumbai 400001 Bandra-Kurla Complex,
Bandra (East), Mumbai 400 051
Scrip Code: 544283 Symbol: ACMESOLAR
Reference: Regulation 30 of the Securities and Exchange Board of India (Listing
Obligations and Disclosure Requirements) Regulations, 2015
Subject: Update on commissioning of Battery Energy Storage System (BESS) Project
Dear Sir/Madam,
In continuation of our intimation dated July 01, 2026, we wish to inform that ACME Solar
Holdings Limited (“ASHL”), through its wholly owned subsidiary i.e. ACME Suryodaya
Private Limited, has commissioned 110.336 MWh capacity of Battery Energy Storage
System (BESS) Project located at Village: Sanwara and Mehar Nagar, Tehsil-Pokhran, Dist:
Jaisalmer, Rajasthan, on July 15, 2026. The Commercial operation date (COD) for the
same shall be July 17, 2026.
With this, ACME Suryodaya Private Limited has achieved a commissioned capacity of 285
MW / 952.960 MWh.
You are requested to take the same on your record.
Thanking you,
For ACME Solar Holdings Limited
Rajesh Sodhi
Company Secretary and Compliance Officer
ACME Solar Holdings Limited
CIN: L40106HR2015PLC102129
Regd.. Office : Plot No .152, Sector-44, Gurugram 122002, Haryana, India
Tel: +91-124-7117000 Fax : +91-124-7117001 Email : cs.acme@acme.in; Website: www.acmesolar.in;