BSECompany Update1d ago · 23 Sept 2026, 09:49 pm
Disclosure under Regulation 30 of SEBI (LODR) Regulations, 2015
Borosil Ltd · 543212
✦ AI SummaryExpansion
Borosil Ltd has delayed the commercial production start from its third double-wall line at its manufacturing unit in Stylenest India Ltd due to logistical and supply-chain constraints.
Analysis Scores
Earnings Impact5/10
Growth Catalyst6/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Borosil Ltd - 543212 - Disclosure Under Regulation 30 Of SEBI (LODR) Regulations, 2015
Attachments (1)
📄pdf
Download →
da2e8067-095e-429e-ab68-6002fbb84fc6.pdf
View document text
September 23, 2026
BSE Limited National Stock Exchange of India Limited
Phiroze Jeejeebhoy Towers, Exchange Plaza, C-1, Block - G,
Dalal Street, Bandra Kurla Complex,
Mumbai - 400 001 Bandra (East), Mumbai - 400 051
Scrip Code: 543212
Symbol: BOROLTD
Dear Sirs,
Sub: Intimation under Regulation 30 of SEBI (Listing Obligations and Disclosure
Requirements) Regulations, 2015
We refer to our earlier intimation dated July 01, 2026, wherein it was, inter alia, informed
that commercial production from the third double-wall line at the manufacturing unit set up
through the Company’s Wholly Owned Subsidiary, Stylenest India Limited, was expected
to commence during Q2 FY 2026-27.
We wish to inform you that the work on the third double-wall line is currently in progress,
and the commencement of commercial production from the said line is now expected by
January 2027. The revised timeline is primarily attributable to certain logistical and supply-
chain constraints in the receipt of imported equipment from China, coupled with the
scheduling and availability of the supplier’s technical personnel for installation and
commissioning.
The Company is closely coordinating with the supplier to expedite the balance activities
relating to installation and commissioning and is taking necessary steps to ensure
completion of the pending activities in line with the revised timeline.
This is for your information and record, please.
This intimation is also being uploaded on the Company's website at www.borosil.com.
Thank you.
Yours faithfully,
For Borosil Limited
Pradeep Joshi
Company Secretary & Compliance Officer
FCS – 4959