G R Infraprojects Limited has informed the Exchange regarding 'Intimation of Declaration of Appointed Date' for a project with the National Highways Authority of India, with an estimated cost of ₹4,262.78 crores and a completion period of 910 days.
Analysis Scores
Earnings Impact5/10
Growth Catalyst6/10
Governance Concern1/10
Regulatory Risk2/10
Balance Sheet Risk3/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
G R Infraprojects Limited has informed the Exchange regarding 'Intimation of Declaration of Appointed Date'.
Attachments (1)
📄pdf
Download →
GRINFRA_18092026172745_Appointed_date_Agra_Gwalior_18092026.pdf
View document text
18th September 2026
BSE Limited National Stock Exchange of India Limited
Phiroze Jeejeebhoy Towers Exchange Plaza, Plot No. C-1
Dalal Street, Fort G Block, Bandra-Kurla Complex, Bandra
Mumbai – 400001 Mumbai -400051
Scrip Code: 543317 Symbol: GRINFRA
Subject: Intimation of declaration of Appointed Date.
Dear Sir,
In accordance with the provisions of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, we are
pleased to inform you that the Company has received a letter dated 18th September 2026 from National Highways Authority of
India, declaring appointed date as 7th September 2026 for the project “Construction of Agra‐ Gwalior Greenfield Road comprising
of: A. Section‐1: Development of 6 Lane of access controlled Agra‐Gwalior greenfield highway, starting from design km 0+000
(near village Deori in district Agra) to design km 88+400 (near village Susera in district Gwalior) in the State of Uttar Pradesh,
Rajasthan and Madhya Pradesh and B. Section‐2: Overlay/Strengthening, other road safety and improvement works on existing
Agra‐ Gwalior section from 1058.00 to 1148.00 (Design chainage 13.00 to 103.00) of NH‐ 44 in the State of Uttar Pradesh,
Rajasthan and Madhya Pradesh on DBFOT pattern at BOT (Toll) Mode under NH(O) scheme.”
Details of the project are as under:
NHAI
Estimated
S. Project Completion Appointed
Name of Project Mode
No. Cost Period Date
(Inclusive of GST)
(INR in Crores)
Construction of Agra- Gwalior Greenfield Road
comprising of:
A. Section-1: Development of 6 Lane of access
controlled Agra-Gwalior greenfield highway, starting
from design km 0+000 (near village Deori in district
Agra) to design km 88+400 (near village Susera in 910 days
DBFOT
district Gwalior) in the State of Uttar Pradesh, from
1. 4,262.78 pattern at 07.09.2026
Rajasthan and Madhya Pradesh and Appointed
BOT (Toll)
B. Section-2: Overlay/Strengthening, other road safety date
and improvement works on existing Agra- Gwalior
section from 1058.00 to 1148.00 (Design chainage
13.00 to 103.00) of NH- 44 in the State of Uttar
Pradesh, Rajasthan and Madhya Pradesh on DBFOT
pattern at BOT (Toll) Mode under NH(O) scheme.
Request you to kindly take the same on record.
Thanking you,
Yours sincerely,
For G R Infraprojects Limited
Sudhir Mutha
Company Secretary
ICSI Membership No. ACS18857