NSEGeneral Updates1d ago · 17 Sept 2026, 02:53 pm
General Updates
Aastha Spintex Limited · AASTHA
✦ AI SummaryExpansion
Aastha Spintex Limited has provided a business update on the execution progress of its 1.35 MW DC rooftop solar PV project at Falcon Yarns Private Limited, which has received GEDA registration and is currently under execution.
Analysis Scores
Earnings Impact2/10
Growth Catalyst6/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk1/10
Liquidity Impact8/10
Market Sentiment5/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Voluntary Business Update under Regulation 30 - GEDA registration and executionprogress of 1.35 MW DC rooftop solar PV project at Falcon Yarns Private Limited
Attachments (1)
📄pdf
Download →
9081535400_17092026145147_Aastha_Spintex_Falcon_Solar_NSE_Announcement_Sign.pdf
View document text
AASTHA SPINTEX LIMITED
Formerly known as Aastha Spintex Private Limited
CIN: L17120GJ2013PLC076361
Registered Office: SURVEY NO 1441 1442 1448/1 1449 1450/2 P2 & 1443/P2, HALVAD MALIYA
HIGH WAY,
SURENDRA NAGAR, HALVAD, GUJARAT-363330, INDIA
https://www.aasthaspintex.com
Email ID: aastha.spintex@gmail.com Mobile: +91 9825192333
Date: 17 September 2026
NSE Limited
Listing Department
“Exchange Plaza”,
Bandra Kurla Complex, Bandra (East),
Mumbai- 400051
Symbol: AASTHA
Subject: Voluntary Business Update under Regulation 30 - GEDA registration and execution
progress of 1.35 MW DC rooftop solar PV project at Falcon Yarns Private Limited
Dear Sir/Madam,
Aastha Spintex Limited ("Company") wishes to provide a business and operational update in relation
to the rooftop solar PV project being implemented at the manufacturing premises of Falcon Yarns
Private Limited ("Falcon"), whose acquisition by the Company has been previously disclosed.
Falcon has received registration from the Gujarat Energy Development Agency ("GEDA") for
installation of a rooftop solar PV system having 1,000 kW AC capacity and 1,350 kW DC capacity (1.35
MW DC) at its Bharudi, Gondal facility in Rajkot district, Gujarat. The GEDA registration is dated 16
September 2026 and has been issued under the Gujarat Integrated Renewable Energy Policy - 2025 for
the industrial/commercial category.
The project has now moved into on-site execution. As per the Daily Progress Report (DPR) dated 16
September 2026, 13 personnel were deployed at site; Module Mounting Structure (MMS) marking
work was approximately 70% complete and MMS installation work was approximately 40% complete.
Photographs of the ongoing rooftop execution are enclosed with this update.
A detailed project note, photographic progress update and copy of the GEDA registration letter are
enclosed as annexures.
Kindly take the above information on record.
For Aastha Spintex Limited
Divyang Jashwant Patel
Din: 03148915
Managing Director
Enclosures:
Annexure I - Detailed Project & Execution Update
Annexure II - Photographic Progress Update
Annexure III - Copy of GEDA Registration Letter dated 1 September 2026
ANNEXURE I
Detailed Project & Execution Update
1.35 MW DC Rooftop Solar PV Project - Falcon Yarns Private Limited
Executive Summary
Falcon Yarns Private Limited has secured GEDA registration for a 1,000 kW AC / 1,350 kW DC rooftop
solar PV system at its industrial facility in Bharudi, Gondal, District Rajkot. The project is registered
under the Gujarat Integrated Renewable Energy Policy - 2025 and is being implemented in CAPEX
mode, with electricity generated intended for Falcon's own use. Physical execution is underway, with
meaningful progress in MMS marking and installation as of 16 September 2026.
Project Snapshot
Applicant / Project Entity Falcon Yarns Private Limited
S. No. 177/1, N.H. 27, near Bharudi Toll Plaza, Bharudi, Taluka
Project Location
Gondal, District Rajkot, Gujarat
GEDA Registration No. PG/HT/10267568
GEDA Registration Date 1 September 2026
Solar PV Capacity 1,000 kW AC / 1,350 kW DC (1.35 MW DC)
Category Industrial / Commercial
CAPEX - system owned by applicant; generated electricity intended
Project Model
for own use
MATgrow Renewables Pvt. Ltd. (as recorded in the GEDA registration
Selected Installer
letter)
DPR / Site Progress Date 16 September 2026
Manpower Deployed 13 personnel
Current Stage On-site execution in progress
Execution Progress as at 16 September 2026
Workstream Progress Status
MMS marking work Approx. 70% Advanced
MMS installation work Approx. 40% In progress
Regulatory Position and Remaining Process
The GEDA letter confirms registration of the rooftop solar PV project. It is important to distinguish
registration from final commissioning. The letter records a number of subsequent technical and
regulatory steps, including:
Technical feasibility assessment by the relevant DISCOM.
Execution of the connectivity agreement with the DISCOM after technical feasibility is established.
Installation of the appropriate bi-directional meter in accordance with DISCOM specifications.
SLD approval and charging permission from the competent electrical authorities, where applicable.
Compliance with the Gujarat Integrated Renewable Energy Policy - 2025, GERC regulations and
applicable ALMM requirements.
Disclosure discipline
Accordingly, the project should be described as "GEDA registered and under execution" rather than
as fully commissioned. The commercial and operating benefits will begin only after completion of
installation, statutory / utility processes and successful commissioning.
Strategic & Operational Relevance
Captive renewable power: The project is registered in CAPEX mode and the electricity generated is
intended for Falcon's own use. This directly links the renewable asset with manufacturing operations
rather than a merchant-power model.
Potential energy-cost efficiency: After commissioning, captive solar generation can reduce the
quantum of grid electricity required during solar-generation hours. Any actual savings will depend on
irradiation, plant availability, captive consumption, tariff structure and other operating factors.
Execution visibility: The DPR and site photographs demonstrate that the project is not limited to a
regulatory application; rooftop marking and mounting-structure installation activity is physically
underway.
Sustainability of manufacturing platform: A dedicated rooftop solar asset can increase the
renewable-energy component of power consumed at the Falcon manufacturing site and supports the
Company's broader focus on operational efficiency and sustainability.
Scalable operating infrastructure: Energy infrastructure at a manufacturing facility is an important
part of supporting production operations. Progress on the solar project strengthens the supporting
infrastructure around the Falcon facility as the broader manufacturing platform is developed.
Current Status / Next Milestones
Regulatory registration Completed - GEDA registration dated 1 September 2026
MMS marking Approx. 70% complete as per DPR dated 16 September 2026
MMS installation Approx. 40% complete as per DPR dated 16 September 2026
Balance installation In progress
To proceed in accordance with technical feasibility and applicable
Utility / statutory steps
approvals
Not yet reported as completed in the information provided for this
Commissioning
disclosure
Forward-looking / qualification note
References to expected operating efficiency, renewable-energy usage or potential energy-cost benefits
are statements of intent and expected operational impact, not guarantees. Actual outcomes may vary
based on commissioning schedule, solar generation, equipment performance, captive consumption,
electricity tariffs, regulatory requirements and other operating conditions.
ANNEXURE II
Photographic Progress Update
Site photographs shared for the DPR dated 16 September 2026
Photograph 1 - On-site execution team carrying out rooftop marking and mounting-structure related
work. The image shows active installation activity across the industrial roof.
Photograph 2 - Wider rooftop view showing multiple MMS work fronts and installation personnel
deployed across the project area.
Photographic Progress Update - Continued
Photograph 3 - Broad rooftop view showing extensive placement / layout of mounting components
across the roof and ongoing execution activity.
Site Progress Summary
DPR Date 16 September 2026
Site Manpower 13 personnel
MMS Marking Approx. 70% completed
MMS Installation Approx. 40% completed
Visual Status Rooftop execution activity visible across multiple work fronts
Management update for stakeholders
The combination of GEDA registration and visible site execution provides a clear milestone-based
update on the project. The next meaningful disclosure milestone would ordinarily be completion of
installation / statutory connectivity processes and successful commissioning, subject to applicable
requirements.