NSECommencement of commercial production/operations10 Sept 2026 · 10 Sept 2026, 06:07 pm
Commencement of commercial production/operations
Juniper Green Energy Limited · JNPR
✦ AI Summary▲ PositiveExpansion
Juniper Green Energy Limited has commissioned 35 MW of wind power capacity, taking its total operational capacity to 175 MWp out of a planned 190 MWp, and increasing its aggregate operational capacity to ~2,639 MWp and ~500 MWh BESS.
Analysis Scores
Earnings Impact8/10
Growth Catalyst9/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment9/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Juniper Green Energy Limited has informed the Exchange about commissioning of additional capacity
Attachments (1)
📄pdf
Download →
JGEL2025_10092026180722_2026_09_10_JGEL_Reg_30_Letter_35_MW_Wind_Capacity_JGEL.pdf
View document text
Date: September 10, 2026
To, To,
National Stock Exchange of India Limited BSE Limited
Exchange Plaza, C-1 Block G, Phiroze Jeejeebhoy Towers,
Bandra-Kurla Complex Bandra (East), Dalal Street,
Mumbai – 400 051 Mumbai - 400 001
Symbol: JNPR Scrip Code: 544853
Sub: Intimation under Regulation 30 of the Securities and Exchange Board of India (Listing
Obligations and Disclosure Requirements) Regulations, 2015 – Update on commissioning of
additional capacity
Dear Sir/ Madam,
This is to inform you that Juniper Green Energy Limited, has commissioned 35 MW of wind power
capacity forming part of its 150 MW Wind Solar Hybrid Power Project at the project site today.
The commissioning has been witnessed and confirmed by officials of Gujarat Energy Development
Agency and Paschim Gujarat Vij Company Limited, and the formal certificate is expected to be issued
shortly. With the commissioning of the aforesaid capacity, our capacity under this project stands at 175
MWp out of total planned capacity of 190 MWp.
Pursuant to the commissioning of the above capacity, the aggregate operational capacity of Juniper
Green Energy Limited and its subsidiaries stands at ~2,639 MWp and ~500 MWh BESS as of the date
hereof.
We request you to kindly take the same on record.
Thanking You,
For Juniper Green Energy Limited
Prashant Pandia
Company Secretary and Compliance Officer
FCS 12077
Juniper Green Energy Limited
(Formerly known as Juniper Green Energy Private Limited)
Registered office: 1103A & 1103B, 11th Floor, Hemkunt Chamber, 89, Nehru Place, New Delhi- 110019
Corporate office: 3rd and 4th Floor, Building 4, Candor TechSpace, Sector 48, Gurugram – 122001, Haryana
CIN: L40100DL2011PLC228318 Email: cs@junipergreenenergy.com; website: www.junipergreenenergy.com/ Tel +91-124 4739600, Fax +91-124 4739666