JSW Energy surpasses 15 GW of capacity milestone; adds 1,572 MW in FY27
JSW Energy Ltd · 533148
✦ AI Summary▲ PositiveExpansion
JSW Energy Ltd has surpassed 15 GW of installed capacity milestone, adding 1,572 MW in FY27, with renewable energy now constituting over 60% of its operational portfolio.
Analysis Scores
Earnings Impact8/10
Growth Catalyst9/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact9/10
Market Sentiment9/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
JSW Energy Ltd - 533148 - JSW Energy Surpasses 15 GW Of Capacity Milestone; Adds 1,572 MW In FY27
Attachments (1)
📄pdf
Download →
1f3a50e6-64ef-4e3b-bc02-9575452f8697.pdf
View document text
Energy Limited
Regd. Office: JSW Centre,
Bandra Kurla Complex,
Bandra (East), Mumbai – 400 051,
CIN: L74999MH1994PLC077041
Phone: 022-4286 1000
Fax: 022-4286 3000
Website: www.jsw.in
SEC / JSWEL
4th September 2026
BSE Limited National Stock Exchange of India Limited
Phiroze Jeejeebhoy Towers Exchange Plaza
Dalal Street Bandra - Kurla Complex, Bandra (E)
Mumbai - 400 001 Mumbai - 400 051
Scrip Code: 533148 Symbol: JSWENERGY
Sub: JSW Energy surpasses 15 GW of capacity milestone; adds 1,572 MW in FY27
Ref: Regulation 30 of the Securities and Exchange Board of India (Listing Obligations
and Disclosure Requirements) Regulations, 2015
Dear Madam / Sir,
This is to inform you that the Company has achieved the significant milestone of crossing
15 GW of installed capacity, following the commissioning of 1,572 MW since April, 2026. The
Company’s total operational capacity now stands at 15,025 MW.
The Press Release in this regard is attached.
Yours faithfully,
For JSW Energy Limited
Monica Chopra
Company Secretary
Part of O.P. Jindal Group
Media Release September 4, 2026
JSW Energy Surpasses 15 GW of Capacity Milestone; Adds 1,572 MW in FY27
Mumbai, India — September 4, 2026 – JSW Energy Limited ("the Company") today announced
crossing the 15 GW installed capacity milestone, post the commissioning of 1,572 MW of
generation capacity since April 2026, increasing its total operational capacity to 15,025 MW. This
milestone was achieved in under six quarters after the Company crossed 10 GW in March 2025,
representing a CAGR of ~26% and underscoring its strong execution capabilities and consistent
progress against its growth roadmap.
The capacity added in FY27 to date comprises 1,272 MW of renewable energy capacity, including
593 MW of solar, 108 MW of wind, 420 MW of hybrid and 150 MW of hydro projects, along with
300 MW of inorganic thermal capacity.
Renewable energy now constitutes over 60% (9,067 MW) of the Company's operational portfolio,
comprising 3,125 MW of wind, 2,426 MW of solar, 1,735 MW of hybrid, and 1,781 MW of hydro
capacity. The thermal portfolio stands at 5,958 MW. The Company remains on track to meet its
greenfield capacity addition target of 3 GW for FY2027, having achieved approximately 42% of
the target to date.
JSW Energy has a total locked-in generation capacity of 32.4 GW — comprising 15.0 GW
operational and 13.4 GW under construction across thermal, hydro, and renewables — along
with a pipeline of 4.0 GW. Locked-in energy storage capacity stands at 29.6 GWh, comprising
26.4 GWh of pumped hydro storage and 3.2 GWh of battery energy storage — positioning the
Company to supply firm, round-the-clock power as the sector shifts from energy to
dispatchability.
The Company is targeting 30 GW of generation capacity and 40 GWh of energy storage by 2030,
and carbon neutrality by 2050.
Page 1 of 2
PRESS RELEASE
ABOUT JSW ENERGY: JSW Energy Ltd is one of the leading Private sector power producers in
India and part of the USD 25 billion JSW Group which has significant presence in sectors such as
steel, energy, infrastructure, cement, sports among others. JSW Energy Ltd has established its
presence across the value chains of power sector with diversified assets in power generation,
and transmission. With strong operations, robust corporate governance and prudent capital
allocation strategies, JSW Energy continues to deliver sustainable growth, and create value for
all stakeholders. JSW Energy began commercial operations in 2000, with the commissioning of
its first 2x130 MW thermal power plants at Vijayanagar, Karnataka. Since then, the company has
steadily enhanced its power generation capacity from 260 MW to 15.0 GW, ensuring diversity in
geographic presence, fuel sources and power off-take arrangements. The Company is presently
constructing various power projects to the tune of 13.4 GW, with a vision to achieve a total power
generation capacity of 30 GW by 2030.
Forward Looking and Cautionary Statements:
Certain statements in this release concerning our future growth prospects are forward looking
statements, which involve a number of risks, and uncertainties that could cause actual results to differ
materially from those in such forward-looking statements. The risks and uncertainties relating to these
statements include, but are not limited to, risks and uncertainties regarding fluctuations in earnings, our
ability to manage growth, intense competition within Power Industry including those factors which may
affect our cost advantage, wage increases in India, our ability to attract and retain highly skilled
professionals, time and cost overruns on fixed-price, fixed-time frame contracts, client concentration,
restrictions on immigration, our ability to manage our internal operations, reduced demand for Power,
our ability to successfully complete and integrate potential acquisitions, liability for damages on our
service contracts, the success of the companies in which JSW Energy has made strategic investments,
withdrawal of fiscal governmental incentives, political instability, legal restrictions on raising capital or
acquiring companies outside India, unauthorized use of our intellectual property and general economic
conditions affecting our industry. The company does not undertake to update any forward-looking
statements that may be made from time to time by or on behalf of the company.