BSECompany Update2 Sept 2026 · 2 Sept 2026, 12:34 pm
Intimation regarding partial Commencement of Commercial Operations at Unit III
Poojaa Precision Engg. Ltd · 544844
✦ AI Summary▲ PositiveExpansion
Poojaa Precision Engg. Ltd has announced the partial commencement of commercial operations at its Unit III, with a melting capacity of 3600 tons p.a. and casting capacity of 1500 tons p.a. The company expects the new unit to increase its manufacturing capacity, enhance operational efficiency, and support business expansion.
Analysis Scores
Earnings Impact6/10
Growth Catalyst8/10
Governance Concern1/10
Regulatory Risk1/10
Balance Sheet Risk2/10
Liquidity Impact8/10
Market Sentiment7/10
✦ Ask a Question
Ask anything about this announcement — AI will answer based on the filing content.
Full Announcement
Poojaa Precision Engg. Ltd - 544844 - Intimation Regarding Partial Commencement Of Commercial Operations At Unit III
Attachments (1)
📄pdf
Download →
2f9d77d0-7ea0-45da-b220-e556b96fbcda.pdf
View document text
Date: 30.08.2026
To, BSE Limited, Phiroze Jeejeebhoy Towers,
Dalal Street, Mumbai - 400 001
Scrip Code: 544844
Symbol: PPEL
Subject: Intimation regarding partial Commencement of Commercial Operations at Unit III
Dear Sir/Madam,
Pursuant to Regulation 30 of the Securities and Exchange Board of India (Listing Obligations and
Disclosure Requirements) Regulations, 2015 (“SEBI LODR Regulations”), we wish to inform you that
Poojaa Precision Engg. Limited (“the Company”) will commence partial commercial operations at its
Gat No.382, 383, 386, 387, 312, Village Amberthan, Tal - Khed, District - Pune – 410501 with effect
from August 30, 2026. Proposed to be installed as per RHP.
The key details are as under:
Particulars Details
Name of the Plant Unit III
Gat No.382, 383, 386, 387, 312, Village Amberthan, Tal -
Location
Khed, District - Pune – 410501
Proposed capacity Melting capacity: 15000 tons p.a
Casting capacity : 6600 tons p.a
Nature of operations Partial installed capacity as on date -
Melting Capacity: 3600 tons p.a.
Casting Capacity :1500 tons p.a.
August 30, 2026.
Date of commencement of
commercial operations
Particulars Details
Melting Capacity: 3600 tons p.a.
Partial Implemented/ installed
Capacity
Casting Capacity: 1500 ton p.a.
Additional capacity, if any Not Applicable
Manufacturing of fully finished Cylinder Heads, EGR Housings,
Products manufactured
Inlet Pipes and other SKUs
Estimated investment till date ₹24 Crore (Rupees Ten Crore only)
Mode of funding equity / Internal accruals / debt / combination
Expected contribution to turnover ₹75 Crore per annum (Rupees Twenty-Five Crore only)
The commencement of operations at Plant No. 3 is expected to increase the Company's
manufacturing capacity, enhance operational efficiency, support business expansion and cater
to increasing customer demand.
The disclosure is being made pursuant to Regulation 30 read with Schedule III of the SEBI LODR
Regulations.
This intimation is also being uploaded on the Company's website in accordance with the applicable
provisions of the SEBI LODR Regulations.
You are requested to kindly take the above information on record.
Thanking you,
For Poojaa Precision Engg. Limited
Shalaka Khandelwal
Company Secretary & Compliance Officer
Membership No.: A62774